Zebulon BPS Generator
PA
Design
Highfill
Infrastructure
Engineering
98%
8/2014
PWS Permit Review
Zebulon Beaver Dam Creek Interceptor
Project
ES
Design
Green
Engineering
95%
TBD
Starting Easement Acquisition
Knightdale Lower Mango Creek
Parallel Interceptor
AB
Construction
Park
Construction
98%
9/2014
Punch List
Wake Forest Richland Creek Parallel
Interceptor
DL
Design
WK Dickson 98%
9/2014
Easements
Wake Forest Smith Creek Parallel
Interceptor
DL
Construction
Park
Construction
0%
12/2015
Contract Routing
Wake Forest I&I Improvements
DL
Construction TA Loving 97% 10/2014
Added N & S Allen Sewer
Martin Pond Road Water Transmission
Main Extension
JG
Design
Withers and
Ravenel
65%
TBD
Easements and
ROW Work
Zebulon Booster PS
ES
Design
Centurion
Construction
15%
9/2014
Installation of a Second Booster
Pump
West Juniper
JS
Bidding
TA Loving
0%
10/2014
Construction Beginning
Zebulon Water Projects
DL
Design
WK Dickson 80%
9/2014
Design in Progress
Various Wendell Gravity Sewer
Extensions
-
-
-
-
-
-
Town of Wake Forest Stadium Dr.
Improvements
JG
Design
Kimley Horn 50%
6/2015
Construction Planned in 2016