PU Monthly Report Volume III Issue II-August - page 28

CITY OF RALEIGH
PUBLIC UTILITIES
Monthly Performance Report
FY 15 (July 2014-June 2015)
28
All financial data is from the city’s financial management system. This is an unaudited report.
Project Name
Project
Manager
Current
Phase
Vendor
%
Completion
Date
Status
NCDOT U-4432 Tryon Road
JG
Construction
NCDOT
0%
-
Pre-Con
August 2014
NCDOT I-440 Crawleigh
JS
Coordination
NCDOT
Vaughn Melton
10%
-
Hammond Rd
Agreement
Public Works Hillsborough Streetscape
JS
Design
Kimley Horn
65%
-
Public Meeting
September 2014
Public Works Capital Blvd.-Spring Forest to
Old Wake Forest
JS
Design
-
10%
-
-
Public Works South and Lenoir 2 Way
Conversion
JG
Design
Kimely Horn
40%
-
Additional Survey
Needed
Public Works Mitchell Mill
JG
Design
Kimley Horn
75%
-
Transportation
Bonds Approved
NCDOT Capital Blvd (Peace St. to Wade Ave)
EN
Design
-
-
-
-
NCDOT/PUBLIC WORKS CONFLICT PROJECTS
Project Name
Project
Manager
Current
Phase
Vendor
%
Completion
Date
Status
Little Creek WWTP Filter Rehabilitation
DL
Construction
Aqua Aerobics
-
-
Contracts Executed
Little River Reservoir Draft EIS
KW
Planning
Hazen & Sawyer 75%
6/2014
Draft EIS in Process
Telemetry System
Improvements Ph. III
PA
Construction
(Phase 3)
CITI
97%
9/2014
Crown Castle Lease
Needed
Smith Creek WWTP
Maintenance Building
ES
Construction SBC Construction 65%
12/2014
Completed Under
Slab Utilities
Sewer Capacity Study
JS
Study
Black and Veatch 99%
Complete
Completing Final
Draft
UFOC East and West Lot Improvements
JG
Construction Riley Contracting 90%
10/2014
Substantial
Completion
VA Security Improvements Phase I & II
PA
Construction
CITI
95%
9/2014
EMJ - Phase II-
90%, Falls Lake
Central Laboratory Study
DL
Study
Hazen & Sawyer 90%
9/2014
Compiling
Laboratory Data
Utility Billing Renovations Lake Woodard
JG
Design
Interior
Architecture
10%
-
Space Study
East Operations
JG
Design
DTW Architects 50%
-
MISCELLANEOUS PROJECTS
1...,18,19,20,21,22,23,24,25,26,27 29,30