4.2.5 Invoicing:

The AOAC Research Institute will issue an invoice for the PTM application

when the PTM Application package is received at the AOAC Research

Institute. The invoice will be on NET 30-day term from the date of the

invoice.

4.2.6 Refunds:

A refund of one-half of the application fee will be made if the Method

Developer withdraws the application prior to acceptance of a contract with

an independent testing site. No refund will be made once a contract with an

independent testing site is agreed to by the Method Developer and signed

by the AOAC Research Institute Managing Director.

4.3

Independent Testing Site:

The Independent Validation Study Protocol is intended to verify the performance of

the test method under controlled laboratory conditions and to characterize the

method under the intended use conditions. A subset of the intended use conditions

claimed by the Method Developer must be evaluated by the independent testing

site.

The Independent Validation Study Proposal must be accepted by all parties before

testing begins. The AOAC-RI will in turn invoice the Method Developer for

reimbursement, separate from the application fee.

4.3.1 Selection of Independent Testing Site:

The Method Developer may ask the Project Manager to request proposals

from more than one independent testing site. Factors in the selection of an

independent testing site can include cost, timing, technical expertise, and

ease of shipping method components and equipment. A testing site will not

be selected to evaluate a particular test method if that testing site routinely

uses the test method under evaluation. Also, the testing site must not have

a financial, corporate, or regulatory relationship with the applicant and must

not be a competitor.

Preference will be given to qualified testing sites accredited to the ISO

17025 requirements for the appropriate field(s) of testing. If evidence of

appropriate accreditation is not provided, on-site visits by a representative of

the AOAC- RI, at the Method Developer’s expense will be conducted to

assess the testing site's compliance with the General Criteria for

Independent Laboratories (Appendix 8).