Background Image
Table of Contents Table of Contents
Previous Page  18 / 64 Next Page
Information
Show Menu
Previous Page 18 / 64 Next Page
Page Background

business & market news

16

TUBE PRODUCTS INTERNATIONAL January 2017

www.read-tpi.com

Bespoke pipe puller aids

multi-duct installation

in Ireland

During April 2016, Stockton Drilling Ltd

(SDL) commenced work on a challenging

crossing of the River Corrib in Galway,

Ireland. The work was completed on a

sub-contract basis for GMC Utilities, the

principle contractor for SSE in Ireland.

The project involved the installation of a

390m-long HDPE pipe bundle beneath

the river to facilitate the installation of a

110kV grid connection to the SSE wind

park west of Galway city. To complete

the work SDL utilised its 250-tonne

horizontal directional drilling rig to install

a bore of 710mm (28") diameter into

which the HDPE pipe bundle was to be

pulled. The HDPE pipe bundle consisted

of three 200mm diameter and three

125mm diameter pipes. The installation

took place at a site located close to the

historic Menlo Castle.

As well as having a width of approxi-

mately 110m, the Corrib flows along a

fault line where two rock types, granite

and limestone, converge. The area is

also a Special Area of Conservation

(SAC). These factors, combined with

works being required not to interfere

with the ongoing activities of the

National University of Ireland Galway

and not to disturb the ruins of the

medieval castle, resulted in the project

presenting an array of logistical and

technical challenges.

In order to overcome these challenges,

the HDD profile was designed as a

continuous curve from the entry point,

entering at 13° to the horizontal and

following a vertical radius of not less

than 400m. To facilitate the reaming

stages of the main bore, two pilot holes

were drilled. Both were installed utilising

a 170mm (6¾") diameter down-hole

mud-motor, powering a 216mm (8½")

diameter tri-cone drill bit to follow the

predetermined profile trajectory to the

pre-planned exit point.

The first pilot hole had a 125mm HDPE

pipeline inserted; this was to be used as

a drilling fluid return line during the main

bore reaming operations. The second

pilot bore was reamed in two stages

to the required 710mm (28") diameter

to facilitate the insertion of the HDPE

pipeline bundle.

In order to install the required pipe

bundle effectively, given the pipe sizes

involved there was a requirement for

a pipe towing head that would pull in

five pipes (3 x 200mm and 2 x 125mm)

at the same time. SDL approached

Pipe Equipment Specialists Ltd (PESL)

for assistance, as this is one of the

company’s specialist areas of operation.

PESL offers a variety of pipe pullers

for various aspects of the pipeline and

trenchless industries. The company’s

Multi Puller is a cone-shaped device

that, within the outer shell, has the

facility to install links to which individual

pipe towing heads can be attached.

However, the job was not going to turn

out to be quite so simple.

Subsequent to the first meeting and the

formulation of the design of the Multi

Puller, SDL added that it wanted to

ballast the pipes in the bundle during

the pull-in operation in order to reduce

the pulling loads, and to minimise

stresses on both the drilling rig and

pipes themselves as the installation

proceeded. Further complicating the

situation, the ballasting would not be

required until the pipe string was about

half way through the pull-in operation of

the HDD process.

Steve Kent, managing director of PESL,

came up with the idea of using the

company’s Test Ends which, when

suitably modified, could be utilised in

the place of standard towing heads.

The Test Ends comprise a pipe end

stop that can be inserted into a pipe

The drill rig launch site on the Galway project showing the pipe bundle

successfully completed pull back

The exit side of the bore showing the pipe

bundle about to be installed