Top projects

Early stage of construction

on the recycle silo.

and ‘switch-over’ challenges which are typi-

cally associated with projects of this nature but

these are known to us and have been properly

planned for,” he says. “We do not anticipate any

impact on day-to-day operations or throughput

at Cullinan while the new plant is being con-

structed as it is being built separately to the

existing plant.”

The new processing plant is not the only

new investment underway at Cullinan. Petra

is also currently busy establishing a new block

cave (C-Cut Phase 1) on the western side of the

orebody in the upper portion of the major C-Cut

resource (estimated to contain some 133 Mct

in total). The project is reportedly progressing

well, with the first rings in the undercut hav-

ing been blasted in June 2015, the deepening

of the men-and-material shaft completed and

the deepening of the ore shaft on track for com-

missioning during H1 FY 2017 (i.e. July to

December 2016).

The C-Cut project, together with a large

tailings operation being developed, will take

annual production at the mine from 0,7 Mct

in FY 2015 to around 2,4 Mct by FY 2019,

with 2,2 Mct being derived from ROM and the

balance from tailings. Petra’s current mine plan

extends to 2030 but major residual resources

indicate that mine life could be in excess of 50

years. Whatever the case, the new plant will

ensure that Cullinan’s needs are catered for in

terms of processing through to the end of its life.

Photos courtesy of Petra Diamonds

Expert Service and Repair. Our extensive service offerings range from full spectrum performance checks, laser alignment, routine on site services and OEM repairs in our internationally certified workshop. We also offer full product support with respect to installations, commissioning and customer training. Your Benefits : OEM after market product support Increased productivity Extended service life Reduced total life cycle cost We also offer training to operating personnel. Contact us for more information Or to set-up an appointment Tel: +27 11 418 4000 www.voith.com V14839