Previous Page  32 / 60 Next Page
Information
Show Menu
Previous Page 32 / 60 Next Page
Page Background

CONSTRUCTION WORLD

JUNE

2017

30

PROJECT PROFILE: ROADS AND BRIDGES

The project which started in March 2016 is on track and scheduled

for completion in the first quarter of 2019. Significantly this project,

an initiative of the South African National Roads Agency SOC

Limited (SANRAL), is currently one of the largest road infrastructure

developments underway in the country.

Scope

It includes the construction of a new two-lane northbound

carriageway, rehabilitation of the existing southbound carriageway

and a large number of structures including bridges, overpasses,

culverts and drainage.

Bulk earthworks will amount to 800 000 m

3

, with layerworks

requiring 400 000 m

3

of material and some 220 000 t of asphalt.

The total concrete volume is 37 000 m³, of which the ancillary works

will use over 16 000 m

3

of concrete.

Contracts manager at Murray & Roberts Infrastructure, Jonathan

Pearce says the project features the full array of civil engineering

activities and includes the construction of 21 major culvert/under

pass extensions and 11 bridges.

The construction of two major river bridges on the northbound

carriageway is on the critical path and work on both has begun.

Preserving the environment

Pearce explains that all the requisite environmental assessments

have been conducted, and construction work is being done in

accordance with these. This is in line with Murray & Roberts

Infrastructure’s solid commitment to preserving the environment

for future generations and ensuring minimum harm to the areas in

which construction is taking place.

The water use licence dictates stringent measures as to how the

rivers may be worked in as well as restrictions to limit the footprint

in and around these areas. In addition, there are strict rehabilitation

programmes in place for after contract completion.

Bridge construction underway

The larger river bridge being constructed is over the Mhlatuze River

which has its source over 100 km away. The river catchment area

supports agricultural and industrial activities before it forms an

estuary as it flows into the deep water port of Richards Bay.

The Mhlatuze Bridge will be 240 metre long and have a total of

70 900 mm diameter bored piles with oscillated liners below seven

piers, some to a depth of 65 metres to reach competent founding

material and ensure adequate load bearing capacity for the final

structure. The bridge construction consists of eight deck spans com-

prising a total of 48 30 metre long post tensioned beams. Each span

has six 1,83 metre high beams which are cast elsewhere on the site.

“Complex geological conditions encountered in this area, with stiff

clay that has similar properties to soft rock found at around

35 metres, has caused delays in completing the piling activity”,

Pearce says.

The stiff clay creates a syringe-like effect on the piling casings

causing complications when liner extraction takes place. “While

delays have put pressure on the construction, we are adapting our

construction schedule to ensure that we meet the deadline and

SANRAL expectations,” he says.

The second major bridge under construction is over the Mlalazi

River and has its own set of challenges, largely emanating from the

inclement weather experienced during February and March this year.

Being so far up the KZN north coast, the tail end of cyclones in the

Madagascan channel normally hit the region bringing heavy rainfall

and major flooding. This was, indeed, the case with cyclone Dineo in

February with rainfall reaching more than 300 mm in 72 hours.

The Mlalazi River is tidal and although the bridge is situated

some 12 km from the ocean, the water level between tides can

rise and fall by up to a metre. Geo-synthetic sand bags have been

used to create working platforms to provide an adequate water

channel with minimum environmental impact while providing safe

working conditions.

The specialised sand bags provide an effective seal between the

water and the construction works, preventing any seepage, such as

unnatural siltation, from the construction site into the river channel.

The Mlalazi Bridge will have a final span of 120 metres with three

piers and two abutments. Ten piles per pier, to a depth of 25 metres

each, will support two of the piers and one abutment. A total of 28

post-tensioned precast beams will be placed on top of the piers

and abutments

“Apart from the John Ross interchange bridge, yet to be

constructed, and the extension to existing overpasses currently

being built in-situ, precast beams will be used. This has allowed the

construction process to be sped up and has negated the need for

extensive scaffolding and formwork along this busy national route,”

Pearce says.

The precast yard is situated in a location that allows the beams

to be easily transported to where required for installation. “Access to

the structural and ancillary works was given special attention as the

bulk of the works could not be accessed from the N2 highway. This

necessitated optimisation of vehicle usage and haulage routes to

remain as productive and cost effective as possible.”

As on all Murray & Roberts Infrastructure sites, safety is a

major focus and on-going safety training ensures that workers

comprehend potential risks associated with construction activities

and how to work towards a Zero Harm goal. On this particular

construction programme, special attention has been placed on

working at height given the number of high structures being built.

“Another mitigating step to ensure optimum safety of workers

on the highway during construction activities was the building of

scaffold towers to enable workers to cross the N2 to the side where

work needs to be done,” Pearce concludes.

Murray & Roberts Infrastructure is a division of Murray & Roberts

Construction which has been purchased by a consortium led by

the Southern Palace Group of Companies, creating the first major

black-owned infrastructure and building construction business in

South Africa.

FIRST BRIDGES ON N2

contract in KZN under construction

By offering an alternative construction methodology,

Murray & Roberts Infrastructure reduced the

proposed construction programme from 40 months

to 37 months on the contract to construct 33 km of

dual carriageway on the N2 between the Mtunzini

Toll Plaza and Empangeni interchange on the

KwaZulu-Natal North coast.

CONSTRUCTION ORLD

JUNE

2017