Previous Page  29 / 60 Next Page
Information
Show Menu
Previous Page 29 / 60 Next Page
Page Background

27

CONSTRUCTION WORLD

JUNE

2017

Another milestone on Africa’s premier wind power project

WorleyParsons reports that the project delivery and

engineering consultancy is nearing completion of

its major scope of work on the Lake Turkana Wind

Power (LTWP) Project in Kenya,

This includes a key milestone of 120 wind turbines attaining Ready

for Energisation (RFE) status in January 2017 and installation of all

365 turbines completed on 5 March in only 362 days.

WorleyParsons’ South Africa team was contracted in Novem-

ber 2014 by the LTWP consortium to provide overall project

management, engineering review and construction management

services for the Lake Turkana Wind Power Project, which will be

the largest wind farm in Africa, and one of the largest in the world,

when completed. The project scope included 365 wind turbines of

850 kW each, an electric grid collection system and a high voltage

substation, upgrades to 210 km of existing road, an internal site

road network and a 160-man self-contained permanent village. The

substation, road infrastructure and village have been completed.

The wind turbines are expected to be commissioned in the last

quarter of 2017 upon completion of the 428 km transmission line

provided by Kenya Electricity Transmission Company.

“Despite some logistical, climatic and community challenges, we

have delivered our scope of work to date for the LTWP Project within

the stipulated timeframe and budget,” says Tim Gaskell, power

business unit manager for WorleyParsons RSA.

“We have worked closely with the customer and with the sub-

contractors to address these challenges and propose workable

solutions. For example, as Lake Turkana is located within a desert-

like environment, it seldom rains, but flash floods do occasionally

occur and the existing road designs did not factor this in. We

assisted with improving the road design to cope with flooding,”

says Gaskell.

“We also deployed additional people to assist local sub-

contractors to adhere to the high standards required for the project.

We have a strong focus on localisation and social upliftment

to ensure that the surrounding communities benefit from this

project, and have placed particular emphasis on health and safety

awareness as most of the local workforce has not been exposed to

any health and safety practices,” adds.

The LTWP Project represents one of the biggest single private

investment in Kenya’s history, and aims to supply 300 MW of reliable,

low-cost wind turbine generator capacity to the Kenyan national grid,

equivalent to about 15% of the country’s current installed electricity

generating capacity.