Previous Page  43 / 60 Next Page
Information
Show Menu
Previous Page 43 / 60 Next Page
Page Background 41 CONSTRUCTION WORLD JUNE 2017

plaza, providing ample scope for both the

consulting engineer and civil contractor, G4

Civils, to refine operations and achieve a

desired production rate over the duration of

the project.

The Stormvoël plaza was next. Located

in a built-up urban area, it required extensive

rerouting of both vehicles and pedestrians.

The relocation of the many services,

including water reticulation, optic-fibre cable

networks and traffic lights, as well as other

temporary and permanent road signs, added

another level of complexity to the project.

Ngqumshe says most of these

challenges were overcome by an extremely

proactive approach taken by JG Afrika and

G4 Civils, prior to mobilising to site.

This was complemented by excellent

team dynamics between both parties right

from the outset.

“G4 Civils is an extremely competent

contractor with a solid track record in road

construction, which was a major advantage

for us. However, we left nothing to chance.

All participants in the professional team

were very aware of the need to plan well in

advance and work together to overcome

any contingencies to the benefit of the

client,” he says.

Pumulani and Doornpoort toll plazas

were next in line and these are due for

completion in March 2017. These two

are followed by the Brits and Marikana

facilities, with the entire project scheduled

for completion in October 2017.

All the new Plazas comprise a 300 milli-

metre-thick concrete pavement supported

by stabilised layers, while structural work

was required to also extend the existing toll

plaza canopies.

This is over-and-above the work required

to install the new signage and signalling

as part of the overall work scope.

The only delays are as a result of the

recent heavy rainfall, reflecting the efficien-

cies of the professional teams on site, and

Ngqumshe is just as pleased by the impres-

sive safety levels maintained throughout

the programme, with no major incidences,

or loss time injuries reported, to date.

This is a significant achievement consider-

ing that the extensions were undertaken in

operational areas, where impatient driving

behaviour and pedestrian movement along-

side the highways were major risks that had

to be thoroughly managed.

He says that successes in this regard

can largely be attributed to the professional

team, G4 Civils, as well as Bakwena’s

emphasis on safety.

“Health and safety have always been

paramount for JG Afrika and G4 Civils, and

our client insisted on this – even if it was at

the expense of production. Bakwena was

well aware of the challenges that we would

encounter in this regard and were, therefore,

more than willing to accommodate any of

our suggestions to ensure a safer site,”

says Ngqumshe.

With a just a few months left before this

project is completed, he believes that it

will be another milestone in the firm’s long

legacy in transport infrastructure, as well as

its close affiliation with both SANRAL

and Bakwena.