Background Image
Previous Page  19 / 60 Next Page
Information
Show Menu
Previous Page 19 / 60 Next Page
Page Background

April 2015

MODERN MINING

17

MINING News

Canada’s B2Gold Corp has announced that

its new Otjikoto gold mine in Namibia

achieved commercial production, ahead of

schedule, on 28 February 2015. The ramp

up of production continues well ahead of

budget.

The open-pit mine poured its first gold

on 11 December 2014, one week ahead

of schedule. In January 2015, the project

continued its strong ramp up to commer-

cial production ahead of schedule and

produced 8 587 ounces against a budget

of 8 267 ounces. Better than budgeted

performance was attributed to additional

mill availability (89,6 % versus budget of

70 %) and better than anticipated through-

put (34 % above budget). February 2015

also saw gold production ahead of target

(10 228 ounces produced versus 8 863

ounces budgeted).

Operating cash costs for the month of

January were US$612 per ounce versus a

budget of US$705 ounce.

For 2015, Otjikoto is expected to pro-

duce between 140 000 and 150 000 ounces

of gold at a cash operating cost of approxi-

mately US$500-525 per ounce and all in

sustaining costs of approximately US$700

per ounce. The company expects annual

gold production to increase to approxi-

mately 200 000 ounces in 2016 and 2017.

New Namibian mine achieves commercial production

The Otjikoto mine poured its first gold on 11 December 2014, one week ahead of schedule (photo: B2Gold Corp).

Expansion of the Otjikoto mill from

2,5 Mt/a to 3,0 Mt/a continues on schedule

with the installation of the first additional

leach tank to be completed during the first

quarter of 2015. Major additional work

that must be completed includes installa-

tion of a second leach tank, construction

of a pebble crusher and associated piping

and pumping components. It is antici-

pated that this work will be completed

by August 31, 2015. This will support

additional throughput initially from the

Otjikoto mine and subsequently from the

fully permitted Wolfshag deposit that is

located immediately adjacent to the main

Otjikoto deposit.

Ferrum Crescent, the direct reduction

iron (DRI) pellet project developer, says it

has determined the final location for infill

drilling and ore reserve development over

Zones A, B and C of the Moonlight deposit,

located in Limpopo Province, South Africa.

These zones have now been selected for

the primary development model over the

first 10 years of mine life.

Drilling over Zone D was the final phase

of comprehensive area drilling undertaken

to identifywhere the next stage of the bank-

able feasibility study (BFS) will be focused.

Zone D drilling confirmed comparable

grades to those previously identified within

the inferred resource, and consequently

the adjacent zones with shallower intersec-

tions, higher grades and better stripping

economics will progress first into develop-

ment. A new mineralised zone outside the

limits of the current JORC (2012) mineral

Mine location identified after drilling

resource was also identified in Zone E.

The drilling programme was a compo-

nent part in the mine design, location and

costing element of the Moonlight BFS. The

BFS was recommenced in Q4 2014 with the

detailed mine plan identified as being the

next core element scheduled for comple-

tion. Following analysis of the 10 RC drill

holes, the first 10-year development model

will be based on Zones A, B and C and fur-

ther infill drilling will commence next to

establish a JORC (2012) ore reserve and

for advanced beneficiation work to be

undertaken as part of the DRI plant design

process. The success of infill drilling will

also determine whether bulk sampling is

necessary to complete the full mine design

and plant costings.

Commenting recently Tom Revy, CEO of

Ferrum Crescent, said: “Following comple-

tion of this phase of mine design drilling,

we have now selected the key zones for

first mine development. Ferrum will work

to establish a full ore reserve and com-

plete advanced metallurgical test work

at Moonlight. Because we are looking to

establish a mining/beneficiation-DRI pellet

manufacturing operation to supply a pre-

mium, high-grade iron product, the current

design phase is especially important as we

progress talks with a number of parties. As

we continue to de-risk Moonlight, by nar-

rowing development parameters, I believe

that the company is well positioned to take

advantage of the significant changes now

occurring within the iron supply market.

“Given the positive advancement of the

BFS and the advanced discussions we have

entered into with three separate parties,

the market looks positive for us to achieve

cash flow by 2019/20.”

Ferrum Crescent is an Australian com-

pany listed on the ASX, London’s AIM and

the JSE.