Background Image
Previous Page  29 / 60 Next Page
Information
Show Menu
Previous Page 29 / 60 Next Page
Page Background

GOLD

April 2015

MODERN MINING

27

The Hummingbird camp at

the Dugbe project in Liberia.

the brink of construction

Hummingbird in a deal worth US$20 mil-

lion,” Betts says. “They’re now the biggest

shareholder in Hummingbird, with a stake of

approximately 25 %. They could have taken

cash but they’ve chosen to retain a significant

interest in the project.”

Hummingbird is planning a smaller devel-

opment than Gold Fields envisaged. “They

were proposing a 3 Mt/a operation but we’ve

scaled it down as we’re targeting the low strip

ratio oxide resources,” Betts explains. “Our

strategy is to get into production fast with a low

cost, low technical risk project which can – if

necessary – be expanded at a later stage. We’ve

optimised all the previous work undertaken on

the project and our Optimisation Study, which

we’ve recently released, indicates very robust

economics for the planned development.”

The optimised project targets 100 000 ounces

of gold production in the first full year after

ramp up and 79 000 ounces a year (on average)

for the balance of the mine life. C1 cash operat-

ing costs are estimated at US$641/oz and all-in

sustaining costs at US$733/oz. Assuming a gold

price of US$1 250/oz, the project will deliver a

post-tax NPV (8 %) of US$72,4 million and an

IRR of 35,1 %. The payback period (after tax) is

put at three years.

Yanfolila has a total gold inventory of

1,8 million ounces, contained in an indicated

resource of 8,2 Mt at a grade of 3,3 g/t and an

inferred resource of 11,9 Mt at 2,5 g/t. The cur-

rent mine plan, however, includes only 6,3 Mt

of ore and is based on progressively mining

five deposits (some of which consist of several

pits): Komana East, Komana West, Guirin West,

Sanioumale East and Sanioumale West.

The plant has been designed to process

1 Mt/a of a 50:50 blend of oxide and fresh ore

giving a likely higher capacity when process-

ing softer oxide ore and offering the potential

to extend the LOM through processing fresh

ore. Hummingbird will contract a mining

service provider to apply industry standard

open-pit mining methods according to its mine

production schedule. A competitive tender is

underway for awarding this contract.

Mining methods will include excavating

the soft oxidised ore near the surface, and

drilling and blasting harder transitional and

some fresh rock – 67 % of ore processed dur-

ing the LOM is oxide ore. Drilling and blasting