Table of Contents Table of Contents
Previous Page  146-147 / 610 Next Page
Information
Show Menu
Previous Page 146-147 / 610 Next Page
Page Background

Benefits

Main Driver

Market Demand

Main Driver Explanation

Projects will enable the reverse flow in all interconnection point

Time Schedule

Grant Obtention Date

25/04/2016

Delay Since Last TYNDP

Delay Explanation

PCI Details

PCI Benefits

Project changes the capability to transmit gas across the borders of the member states concerned by at least 10%, compared to the situation

prior to the commissioning of the project, Project concerns investment in reverse flow capacity

General Criteria Fulfilled

Yes

Specific Criteria Fulfilled

Competition, Market Integration, Security of Supply, Sustainability

Specific Criteria Fulfilled Comments

TRA-F-86

Interconnection Croatia/Slovenia (Lučko - Zabok - Rogatec)

TRA-F-334 Compressor station 1 at the Croatian gas transmission system

Schedule

Start Date

End Date

Pre-Feasibility

Feasibility

FEED

Market Test

Permitting

01/2017

01/2020

Supply Contracts

FID

01/2018

Construction

01/2018

01/2020

Commissioning

2020

2020

NDP and PCI Information

Part of NDP

Yes (2017-2026)

NDP Number

5.2 and 5.3

Currently PCI

Yes (6.26.3)

CBCA Decision

No

Market Survey

Not Relevant (no CBCA decision)

Third-Party Access Regime

Considered TPA Regime

Not Applicable

Considered Tariff Regime

Not Applicable

Applied for Exemption

Not Relevant

Exemption Granted

Not Relevant

Exemption in entry direction

0.00%

Exemption in exit direction

0.00%

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM

Page 300 of 620

Current TYNDP : TYNDP 2017 - Annex A

Southern Corridor GRIP 2017–2026 Annex B |

74