Eastring - Slovakia

TRA-N-628

Project

Pipeline including CS

Non-FID

Update Date

25/05/2016

Non-Advanced

Description

Eastring-SK is subproject located in Slovakia/Ukraine and is essential part of the Eastring project, which connects IP Veľké Kapušany at the SK-UA

border, with a new entry IP at an external border of the EU on the territory of Bulgaria in the following routing options: − from SK to RO − via UA,

(exist. pipeline) − via HU, (new pipeline). − from RO to TR − Option A – new pipeline passing production & storage area and continuing to IP Isaccea

and to BG/TR border by utilizing existing RO-BG transit assets − Option B – new pipeline, passing 2 production & storage areas and continuing to an

external border of the EU on the territory of Bulgaria. The project would (i) secure supplies in case of RU disruption and therefore it will increase gas

SoS in the broader Central-South-East EU region, (ii) allow access to alternative gas sources for Central, Western & Southern Europe and (iii) mean

step towards EU single gas market.

Regulatory Decisions and

similar material conditions

Capacity Increments Variant For Modelling

Variant : Eastring - SK-2

High capacity scenario, starting at Veľké Kapušany IP and passing through SK using new

pipeline to new IP at SK-HU border

Point

Operator

Year

From Gas System To Gas System Capacity

Eastring Cross-Border HU/EAR <> SK/EAR

Eastring B.V.

2021

HU/EAR

SK/EAR

570.0 GWh/d

Comment: New interconnection point, New capacity increment from 4Q 2025 to the level of

1140 GWh/d.

Eastring B.V.

2021

SK/EAR

HU/EAR

570.0 GWh/d

Comment: New interconnection point, New capacity increment from 4Q 2025 to the level of

1140 GWh/d.

Eastring B.V.

2025

HU/EAR

SK/EAR

570.0 GWh/d

Eastring B.V.

2025

SK/EAR

HU/EAR

570.0 GWh/d

Eastring SK/EAR <-> Veľké Kapušany

Eastring B.V.

2021

SK

SK/EAR

570.0 GWh/d

Comment: Connection of Eastring - SK to existing SK transmission system at Veľké Kapušany IP

(VK), New capacity increment from 4Q 2025 to the level of 1140 GWh/d.

Eastring B.V.

2021

SK/EAR

SK

570.0 GWh/d

Comment: Connection of Eastring - SK to existing SK transmission system at Veľké Kapušany IP

(VK), New capacity increment from 4Q 2025 to the level of 1140 GWh/d.

Eastring B.V.

2025

SK

SK/EAR

570.0 GWh/d

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM