Table of Contents Table of Contents
Previous Page  560-561 / 610 Next Page
Information
Show Menu
Previous Page 560-561 / 610 Next Page
Page Background

CS Kidričevo, 2nd phase of upgrade

General Information

Promoter

Plinovodi d.o.o.

Operator

Plinovodi d.o.o.

Host Country

Slovenia

Status

Planned

Website

Project's URL

Publication Approval Status

Approved

Sponsors

Plinovodi

100%

TRA-N-094

Project

Pipeline including CS

Non-FID

Update Date

22/05/2016

Non-Advanced

Description

Upgrade of CS for higher operational pressure in existing M1/1 and M2/1 pipelines, higher flow and bidirectional operation. The project aims to

assure additional necessary compressor power for the PCI 6.26 Cluster Croatia - Slovenia - Austria at Rogatec.

Regulatory Decisions and

similar material conditions

Enabled Projects

Project Code Project Name

TRA-N-390 Upgrade of Rogatec interconnection (M1A/1 Interconnection Rogatec)

TRA-N-389 Upgrade of Murfeld/Ceršak interconnection (M1/3 Interconnection Ceršak)

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM

Page 509 of 620

Current TYNDP : TYNDP 2017 - Annex A

Southern Corridor GRIP 2017–2026 Annex B |

281