introduction FY2014

Train Depot (Railroad Town)

Project Description: Design and construct a replica of 1800's Train Depot in the Town Center identifying the town as a Railroad Town.

Town Goals

Manage Resources

Invest in Infrastructure and Transportation

Serve the Community

Provide an EnvironmentallySensitive & Livable Community

Serve the Community

Foster a Healthy Community

Run the Operations

Model a Positive Town Image

Benefits of Project:

Lead Department:

Public Works Department

1. Commemorate Morrisville's origins as a depot village

Date Added to CIP:

2009

2. Enhance the historic character of the Crossroads area

Review Date:

15-Mar-09

3. Help mark the gateway into the Town Center core

Design Start Year:

2020

4. Create a distinctive space to tell the railroad history of the town

Construction Start Year:

2021

5. Help draw visitors to Morrisville

Estimated Project Costs:

$4,395,692

Additional Staffing Required:

No

Number of New Positions:

0

Operations and Maintenance Estimates

2022

2023

2024

2025

2026

O&M Remarks:

Equipment and Furniture

Utilities

Maintenance

Supplies

Personnel

Other Funding

Sources and

Related Revenue

Projections

None

Financing Plan

Installment 10

Tax on $100k

Debt Service Schedule

Tax Base

¢ Tax

$

102.20

1 2022

$

537,652 $ 4,299,514,804

1.25

$

12.50

2 2023

$

537,652 $ 4,428,500,249

1.21

$

12.10

3 2024

$

537,652 $ 4,561,355,256

1.18

$

11.80

4 2025

$

537,652 $ 5,245,558,544

1.02

$

10.20

5 2026

$

537,652 $ 5,402,925,301

1.00

$

10.00

6 2027

$

537,652 $ 5,565,013,060

0.97

$

9.70

7 2028

$

537,652 $ 5,731,963,452

0.94

$

9.40

8 2029

$

537,652 $ 5,903,922,355

0.91

$

9.10

9 2030

$

537,652 $ 6,081,040,026

0.88

$

8.80

10

2031

$

537,652 $ 6,263,471,227

0.86

$

8.60

11

2032

$

- $ 6,451,375,363

0.00

$

-

12

2033

$

- $ 7,096,512,900

0.00

$

-

13

2034

$

- $ 7,238,443,158

0.00

$

-

14

2035

$

- $ 7,383,212,021

0.00

$

-

15

2036

$

- $ 7,530,876,261

0.00

$

-

16

2037

$

- $ 7,681,493,786

0.00

$

-

17

2038

$

- $ 7,835,123,662

0.00

$

-

18

2039

$

- $ 7,991,826,135

0.00

$

-

19

2040

$

- $ 8,151,662,658

0.00

$

-

20

2041

$

- $ 8,966,828,924

0.00

$

-

Comments:

Ed Lynch needed here per BH to better estimate project cost and location. - Include land acquisition.

Town Center Projects

Priority

24.0199241

Total Group Projects

0

Total Projects

0

Town Priority

Project Number

1360

48