Background Image
Previous Page  12 / 56 Next Page
Information
Show Menu
Previous Page 12 / 56 Next Page
Page Background

10

MODERN MINING

October 2015

MINING News

ASX-listed Kimberley Diamonds Ltd (KDL)

has announced that its Botswana sub-

sidiary, Lerala Diamond Mines Limited,

recently held a site ‘blessing ceremony’

with the local community at the Lerala

diamond mine. The ceremony was held

at the request of the local community and

was aimed at mobilising the community to

provide its support and best wishes for the

success of the mine.

KDL is in the process of re-establishing

Lerala, located in Botswana close to the

Martins Drift border post with South Africa.

The process plant is currently undergoing

a major refurbishment and re-engineering,

prior to recommissioning.

Approximately 400 people attended

the blessing ceremony, which was led

by Lerala’s Chief Moroka. Also in atten-

dance were his 16 sub-chiefs, several

pastors and chairpersons from the Village

Development Community. Several mem-

bers of KDL’s leadership team were also

present, including Noel Halgreen, KDL’s

Managing Director.

KDL has also provided an update on

its preparation for the resumption of min-

ing operations at Lerala. The mine has five

diamond bearing kimberlite pipes to be

mined, K2, K3, K4, K5 and K6. Mining is

currently scheduled to start early in 2016

in the K3 pit. During the time Lerala was

on care and maintenance, the K3 pit was

allowed to fill with groundwater and act as

a water storage facility. With the planned

commencement of mining activities in

Community turns out in support of diamond mine

Members of the local Lerala community, visiting pastors and KDL senior management at the blessing ceremony

held on site recently (photo: KDL).

the K3 pit, a dewatering exercise began

in February 2015 to pump all water from

the K3 pit out to the K6 pit, where it will

be stored until potentially required for pro-

cessing operations.

Pumping has been ongoing for the

past seven months and water is now suf-

ficiently cleared so that mining operations

can commence as soon as required.

With the water cleared from the K3

pit, this has facilitated better access and

enabled a detailed geotechnical mapping

exercise to be undertaken in this pit by a

consulting geotechnical engineer, who

will confirm the slope stability parameters

to provide for updated open-pit designs.

Geotechnical mapping was conducted

in the K2 and K5 pits, which are scheduled

to be mined early in the mining schedule

at Lerala. The preliminary geotechnical

assessment results suggest that there is

scope for improving the design param-

eters and reducing pit stripping ratios,

which KDL anticipates will reduce overall

mining costs.

Once the preliminary report with rec-

ommended slope design parameters for

each pit is received from the geotechnical

consultant, KDL plans to undertake a min-

ing optimisation exercise.

According to KDL, all aspects of the

Lerala project are progressing very well to

date and remain on schedule. KDL believes

that if this progress can be maintained and

barring any unforeseen delays, this will see

the project well prepared for re-commis-

sioning early in 2016.

Clean energy power plant at Waterval opened

Anglo American Platinum, together with

Vuselela Energy and H1 Holdings, recently

officially opened a clean energy power

plant, Eternity Power, at its Waterval

Smelting Complex in Rustenburg.

The project was made possible by the

Department of Trade and Industry (DTI)

providing a R30-million grant as part of

its Infrastructure Development Support

which leverages investments to the South

African economy by providing infrastruc-

ture critical to industrial development. The

incentive programme is part of the Critical

Infrastructure Programme (CIP).

The Eternity Power Thermal Harvesting™

project was commissioned in June 2015

and developed by Vuselela Energy in col-

laboration with Anglo American Platinum

at a total project cost of R150 million.

This ground-breaking initiative uses

waste heat from the Anglo Converter Plant

(ACP) convertor cooling circuit to evaporate

an organic liquid and drive an expansion

turbine. The plant has an installed capacity

of 5 MW of which 4,3 MW is available to the

grid, reducing Anglo American Platinum’s

capacity bought from Eskom. The amount

of power generated also results in a reduc-

tion of the smelter’s carbon footprint and a

more efficient use of energy.

Jacques Malan, Director at Eternity

Power and Vuselela Energy, said: “The set

of technologies used at the Eternity Power

clean energy plant had not previously been

used in a smelter environment and a sig-

nificant amount of novel work was done to

design the integration of the technology

into the smelter complex and to establish

the technical feasibility of the process.

“These patents were developed spe-

cifically for the purpose of capturing and

harnessing waste thermal energies from

metallurgical and chemical processes for

the purpose of power generation and

are likely also patentable worldwide. The

result is that the Eternity Power Thermal

Harvesting™ power plant is the first of its

kind in the world in terms of being con-

nected to a convertor at a metallurgical

smelter.”