Background Image
Previous Page  7 / 56 Next Page
Information
Show Menu
Previous Page 7 / 56 Next Page
Page Background

October 2015

MODERN MINING

5

MINING News

Estimate. Prior to milling operations

commencing, it is planned to have over

400 000 tonnes of ore at reserve grade on

the stockpiles, which is in excess of one

month’s production requirements.

Pit dewatering has continued to

advance ahead of the mining operations

with 4,6 million m

3

of the expected 6 mil-

lion m

3

of water now pumped from the

Nkran pit (approximately 77 %). The pit is

expected to be empty in November. Pit

dewatering boreholes are currently being

drilled and will be operational as required

during Q4 2015.

Installation of the primary crusher has

been completed, with work focusing on

the structural, mechanical and platework.

The concrete work for the run-of-mine tip

wall and erection of the primary tip bin at

the primary crusher have also been com-

pleted. Installation of the apron feeder and

other mechanical equipment is underway.

The stockpile feed conveyor was due to

be finished by the end of September. The

stockpile tunnel is complete and the mill

feed conveyor is being assembled. It is

expected that the crusher and stockpile will

be ready for commissioning on low-grade

ore in Q4 2015.

In the milling section, the shells for both

the SAG and ball mills have been installed

and the associated steelwork is nearing

completion. The SAG mill discharge sump

is in place, as well as the vibrating screens.

The carbon-in-leach circuit is continu-

ing to progress with all seven tanks fully

erected and interconnecting steel and

platework also in place.

The Tailings Storage Facility (TSF) is

over 95 % complete and will be inspected

by an independent third party this month

(October). The final inspection report will

allow the company to meet its last per-

mit condition and the TSF will be ready to

accept tailings. It is expected that the TSF

will be utilised for storing water for use in

the start-up and commissioning.

In June 2015 Asanko signed a life

of mine, fixed-priced power purchase

agreement with the independent

power producer Genser Energy Ghana

for the supply of 17 MW to Phase 1.

Commissioning of the power plant is

targeted for April 2016. Until the main

power plant is operational, Genser will

provide temporary power to Phase 1 via

five 5 MW semi-mobile, liquid natural gas-

fired generator units. The five generators

are expected to arrive on site this month

(October) and will take approximately two

weeks to install and commission.

In addition to the dedicated power

plant, the company has also constructed a

161 kV power line which connects to the

main power grid. The line will be used to

deliver excess power from the dedicated

power plant into the grid, or to provide

a back-up source of power for the opera-

tions. All the power line towers over the

30 km line length have been erected

and stringing of the power line is 80 %

complete.

The main EPCM contractor, DRA Global,

continued its excellent safety record with a

recent achievement of 2,4 million lost time

injury free man hours.

Peer Review validates process route for Kabwe project

AIM-listed BMR Mining has reported the

principal conclusion of a Peer Review of its

Kabwe treatment project in Zambia.

BMR engaged the services of Tony

Francis of Francis Minerals Consulting

Limited to undertake a Peer Review of the

company’s proposed processing method-

ology for producing lead and zinc from the

Kabwe tailings. Francis visited BMR’s Kabwe

operation between 27 and 31 August 2015.

According to BMR, the Peer Review has

confirmed the suitability of BMR’s acid/

brine leach process for the recovery of

these metals. BMR is currently finalising

both its processing plans, which will be

submitted to ZEMA (Zambia Environmental

Management Agency) in the near future,

and its costings of the pilot plant.

BMR plans that the treatment rate for

the pilot plant will be a minimum of 5 t/h.

It intends that it will be operated on a 24/7

basis, initially processing the wash plant

tailings.

The principal objective of the pilot plant

will be to finalise the design parameters of

the proposed main plant, which is planned

to come into operation in 2016, to enable it

to process different combinations of tailings.

Nevertheless, BMR’s intention is to operate

the pilot plant as a semi-production unit

to simulate actual operating conditions,

thereby enabling the company to generate

revenues from sales of the end product.

BMR also reports that it has entered

into an agreement with Sable Zinc Kabwe,

a subsidiary of Glencore, in respect of land

adjacent to BMR’s tailings dumps and cer-

tain key items of equipment.

The agreement, which has an initial

term of 12 months, provides for the lease

by BMR, at a cost of US$1 000 per month, of

a concrete apron on which the pilot plant

will be sited. The plant will include a 300 m

3

partially rubber-lined reservoir suitable for

the storage of re-cycled water, three 90 m

3

rubber-lined leach tanks, a 60 m

3

rubber-

lined clarifier and rake mechanism, and a

filter press.