Previous Page  34 / 60 Next Page
Information
Show Menu
Previous Page 34 / 60 Next Page
Page Background

32

CONSTRUCTION WORLD

MAY

2016

PROJECT PROFILE

>

Following the completion of

another civil engineering construc-

tion contract at the iron ore mine

later this year, the leading South

African infrastructure specialist, which forms

part of Murray & Roberts Construction, will be

establishing itself elsewhere in the country to

start working on a road construction contract

for a major local roads agency.

Murray & Roberts Infrastructure recently

completed the civils works for the mine’s new

Heavy Mining Equipment filling station and

storage tank area. This infrastructure will be

used to service the giant Komatsu rigid dump

trucks that haul iron ore out of the pit to the

tipping point.

Murray & Roberts Infrastructure’s

contracts manager, Tiaan Krugel, says one

of the complexities of this project was the

number of working faces on the contract

and the extremely fast track nature of the

project, which was completed in as little as

six months.

“The biggest challenge we faced on this

contract was the number of working faces from

day one. There were at least 10 at any given

time during the project duration,” he says.

Coping with the formidable task at

hand called for excellent team work, and

Krugel notes that the client’s involvement

helped tremendously.

“The client did a great job in terms of

managing the project. It was extremely proac-

tive, which helped us moving forward.”

The contracting team also had to take a

proactive approach to managing the arrival

of a host of built-in and cast-in items for the

project. While lead times for some items, such

as the pipelines, are 12 weeks, he says that

the biggest hurdles occur before the actual

order is placed with the vendors. All docu-

mentation can take up to 18 weeks to finalise

to receive the necessary permission to have

the items delivered to site.

“Sometimes, it can take between three

and four months before you get everything

to site, so you have to plan very carefully”

says Krugel.

Big pours

One of the highlights of the build was the

600 mm concrete slab that makes up the

forecourt of the filling station. Constructing

the 90 metre by 66 metre forecourt called for

the placement of 4 800 m

3

of concrete – with

a total of 8 000 m

3

poured – and 570 tons of

reinforcing bar – with a total of 770 tons for

the entire project.

Between six and eight readymix trucks

ran to and from the batching site a day.

The sheer number of trucks was necessary

considering that 3Q Concrete’s batching plant

is located eight kilometres from the site.

A total of 18 pours were needed to

complete this aspect of the works with the

HME FILLING STATION

at Sishen

Work may have been undertaken outside the

so-called ‘red zone’ at Sishen mine in the

Northern Cape, but this did not make one of the

last contracts Murray & Roberts Infrastructure

undertook for Kumba any easier.