Previous Page  35 / 60 Next Page
Information
Show Menu
Previous Page 35 / 60 Next Page
Page Background

33

CONSTRUCTION WORLD

MAY

2016

ABOVE LEFT:

One of the challenges was

managing the workability and behaviour of

the concrete in the cold winter months when the

pours were done.

ABOVE:

As many as 10 different interfaces were

on the go at any given time.

RIGHT:

The concrete crews would start pouring at

7:00 in the morning with their shifts varying from

nine to 12 hours.

biggest comprising a massive 420 m

3

in

12 hours. Generally, the Murray & Roberts

Infrastructure team would average between

200 m

3

and 400 m

3

in a shift

The slab was constructed in 18 panels,

each of which comprised roughly 33 metre

by 10 metre sections with various slopes to

allow for surface drainage. It also comprises

various islands and plinths to accommodate

the mechanical installations.

Major concrete works were also under-

taken at the 1 500 m

2

diesel and lubrication

storage tank area. The contractor built

two 12,7 metre diameter ring beams to

support two 1 500 k

diesel tanks, as well

as a 2,2 metre high bund wall on the peri-

meter of the area.

This aspect of the work also comprised

surface slabs adjoining the three sides of the

structure, with multiple plinths to accommo-

date the mechanical installations.

Krugel says one of the challenges on all

concrete works undertaken in the area was

the extreme fluctuations in temperature.