Cold winter season
Although many of the complexities encoun-
tered could be attributed to the cold winter
season when asphalt batching started, one
of the biggest challenges was the excessive
fines generated at the plant. It was possible
through close collaboration between the
contractor and the supplier to solve this,
and the company is now able to meet the
very onerous RA requirements on other road
construction contracts moving forward.
Also playing an invaluable role in keeping
works on track was the specific focus areas of
each participant in the consortium.
Raubex deployed its own team whose
responsibilities ended with the priming
of layers, after which Roadmac Surfacing
commences operations that end with the
The Raubex Construction and Roadmac Surfacing team.
One of the successes of this project is the focus areas of each member of the consortium, with Roadmac
Surfacing placing all of its attention on the asphalt.