PREFACE

Prior to the involvement of the LOPA sub-group, I had conducted a LOPA study for a

client with a large storage facility located on the Humber estuary, the study had not

been completed, so in discussions with the Terminal Manager, he agreed that we

could use his Terminal to facilitate the work of the PSLG.

The LOPA report had been conducted and issued with four revisions:

1. The Original issue

2. Revised with multiple initiating events

3. Clients comments added

4. SIL 2 IPL data added

In February 2009 the LOPA working party visited the site.