Previous Page  24 / 56 Next Page
Information
Show Menu
Previous Page 24 / 56 Next Page
Page Background

GOLD

22

MODERN MINING

March 2017

View of the Yanfolila site

(prior to erection of the

tower crane) showing work

on the CIL tank foundations.

economics of Yanfolila have clearly appealed

to the market and last year we were able to

raise US$71 million in equity and US$45 mil-

lion in debt to fully fund the project through

to production. This allowed us to embark on

full-scale construction – as opposed to earlier

preparatory earthworks – in October 2016,

when the first concrete was poured. Our

equity raising, incidentally, was the biggest

by an AIM-listed gold company in the past

four years.”

A key step in the development of Yanfolila

was the appointment in July last year of South

African project house SENET – involved in

the project since the Gold Fields days – as the

EPCM contractor to build the plant and asso-

ciated infrastructure. SENET, of course, boasts

considerable West African experience, hav-

ing worked – amongst others – on Randgold’s

Loulo and Tongon projects in Mali and Côte

d’Ivoire respectively, as well as (more recently)

the Karma gold project in Burkina Faso of True

Gold (now part of Endeavour Mining).

Hummingbird followed up in September

with the appointment of IMAGRI-SARL – a

Malian contractor – as the civil works contrac-

tor (it is now responsible for the SMPP works as

well) and in December announced that African

Mining Services (AMS), a subsidiary of ASX-

listed Ausdrill, had been selected as the mining

contractor.

AMS is highly experienced in West African

gold mining with a track record in the region

going back 25 years. Its contract is for an ini-

tial three-year period and has a total value of

US$112 million. The company will be deploy-

ing a new mining fleet of mainly Caterpillar

equipment worth US$38 million and will

employ in the region of 450 people (mostly

Malians) once it begins operations. Mining is

due to commence in September this year, with

the ore initially being stockpiled in advance of

plant commissioning. At peak production dur-

ing the first three years of mine life, the mining

schedule calls for approximately a million bank

cubic metres to be mined monthly.

The mining will be a conventional drill-and-

blast, load-and-haul operation with the deep

oxide and transitional zones making for an

easy start-up. The first pits to be mined will be

Komana East and Komana West but ultimately

three further pits will be brought into the mix

– Guirin West and Sanioumale West and East.

The Komana East pit has the biggest reserve –

230 koz at a grade of 3,06 g/t.

Recovery of gold will be through a com-

bination of gravimetric means and direct

cyanidation. Gravity concentrate is treated

through an intensive cyanidation process with

the pregnant solution pumped to an indepen-

dent gravity electrowinning circuit. The CIL

circuit consists of seven tanks in series: one

pre-leach tank and six CIL tanks. The plant is

expected to deliver a gold recovery of 92,5 %.

A two-stage crushing circuit is being

installed to treat all ore types. In order to main-

tain mill throughput, a tertiary crushing facility

will be added when the proportion of hard

fresh ore increases. A 12-hour live stockpile

will ensure continuous and consistent feed to

the mill.

Among the companies supplying equipment

for the plant are Metso (crushing circuit equip-

ment), Outotec (ball mill), Afromix (agitators)

and Kemix (screens and carbon regeneration

kiln). To supply power, the mine will need

a 6,5 MW capacity diesel genset facility. It

is anticipated that this will be provided by

an Independent Power Provider (IPP) and

Hummingbird is currently negotiating with

potential partners.

With mine operations not too distant now,

Hummingbird has started appointing the

permanent staff who will run the mine and

in February this year announced that Kevin

Moxham had been employed as General

Manager. He is hugely experienced in min-

ing – in particular gold mining – and was

At peak

production during

the first three

years of mine

life, the mining

schedule calls for

approximately

a million bank

cubic metres to be

mined monthly.