Background Image
Previous Page  15 / 72 Next Page
Information
Show Menu
Previous Page 15 / 72 Next Page
Page Background

August 2015

MODERN MINING

13

MINING News

limited processing of material from vari-

ous larger size fractions throughout the

later part of the period. The initial pro-

cessing of larger size fractions during the

commissioning of the upgrades provided

the company with important insight into

the processing of this material, its impact

on the processing of other sized material,

and the combined impact on operational

efficiencies overall.

Diamcor says its focus will now shift

to increasing processing volumes, the

size fractions of material being processed

(with consideration for above larger

material cut-off size), and a move towards

advancing objectives consistent with

the recommendations of the updated

NI43‑101 Technical Report filed by the

company in April this year.

The Krone-Endora at Venetia project

is located directly adjacent to De Beers’

flagship Venetia mine, and the associated

deposits have been identified as being

the result of the direct-shift and erosion

of material from the higher grounds of the

adjacent Venetia kimberlite areas.

Mwana Africa’s profits deteriorate sharply

Mwana Africa, which operates mines in

Zimbabwe, has announced improved con-

solidated revenue of US$152,3 million for

the financial year to 31 March 2015. It says

this was achieved even though the year pre-

sented particular challenges of falling gold

and nickel prices, challenges that have per-

sisted beyond the end of the financial year.

Consolidated profits deteriorated

sharply with a number of operational set-

backs that contributed to higher unit costs.

The group’s net profit fell to US$7,0 million

from the preceding year’s US$50,6 mil-

lion, although there was a US$28 million

impairment reversal in the prior year, which

contributed to higher profits.

At the Freda Rebecca gold mine, pro-

duction stagnated as a result of equipment

failures that needed to be addressed and

improvements that were effected on an ad

hoc basis.

These technical problems were par-

alleled at Bindura Nickel’s Trojan mine

where a large part of the mine’s equipment

had been allowed to deteriorate during

the period of care and maintenance and

needed to be progressively refurbished and

replaced throughout the year.

The planned re-start of Bindura Nickel’s

smelter was initiated during the past year at

a budgeted cost of US$22million, with inter-

nal financing augmented by the issue of a

US$20 million five-year bond. The smelter

will have the capacity to process Trojan’s

own concentrates and to toll-treat outsiders’

concentrates to produce nickel leach alloy.

The bond will be serviced from revenues

enhanced by the smelter’s operations.

In South Africa, while the recovery

of diamonds at the Klipspringer residue

treatment joint venture reached planned

capacity, this was less than anticipated.

Consideration is now being given to the

reprocessing of coarser tailings and to an

eventual reopening of underground opera-

tions on the mine’s Leopard fissure.