Background Image
Previous Page  16 / 72 Next Page
Information
Show Menu
Previous Page 16 / 72 Next Page
Page Background

14

MODERN MINING

August 2015

MINING News

Platinum Group Metals (PTM), listed

on the TSX and NYSE, reports that its

82,9 %-owned WBJV Project 1 platinum

mine (Maseve) located near Rustenburg

is approximately 90 % complete and is

on track for planned production in 2015.

Cold commissioning of processing plant

equipment is planned for this month

(August) with initial concentrate produc-

tion on track for the fourth quarter of

calendar 2015.

The mineral resources and mineral

reserves for Project 1 have been updated

to account for the planned increased use

of mechanised mining methods where

the deposit is estimated to be thicker and

accessible from nearby completed under-

ground development.

Production guidance for fiscal 2016 is

116 000 ounces platinum, palladium, rho-

dium and gold (4E) (100 % project basis)

and 185 000 ounces 4E in fiscal 2017 in

concentrate. Steady state has been esti-

mated to be 250 000 ounces 4E per year.

Exclusive of smelter discount, on site

costs are estimated to be US$526 per 4E

ounce for the life of mine on the Merensky

Reef including copper, nickel and other

minor elements as a credit and US$774 per

4E ounce on the UG2.

Comments R Michael Jones, CEO of

PTM: “We have done well at 90 % comple-

tion on the project construction utilising a

well-known plant design and our proven

team. We are operationally ready with

our experienced owner’s team. We

have updated our mine plan for current

underground development and updated

mineral resources and mineral reserves.

Underground trackless mechanised devel-

opment is planned to be used for more of

the mining as compared to our original

design, thereby improving ramp up and

flexibility.”

The revised mine plan takes advan-

tage of recently advanced underground

development proximal to thicker, deeper

mine blocks as compared to the shallower

more variable blocks mined in the original

design. PTM expects that the adoption

of mechanised and hybrid mining

approaches will allow for a rapid ramp-

Recent photo of the Maseve processing plant. It has a capacity of 110 ktpm but allowance has been made for this to be increased to 160 ktpm (photo: Platinum

Group Metals).

Maseve now in the final straight

up of production with significantly lower

waste rock development compared to

the conventional mining method that the

company had planned to use previously.

PTM expects that dilution resulting from

the mechanised approach, along with

new block information, will result in a 17 %

lower grade on the early mined Merensky

ore, which is largely offset by lower waste

rock development and costs.

Approximately 1 900 people are cur-

rently on site. Surface construction

manpower is expected to decline as the

underground work force increases over the

coming months. Safety has been and con-

tinues to be a priority. The current safety

record is better than the industry average

with approximately 2,6 lost time injuries

per million man hours worked.

As mentioned, initial production of con-

centrate is planned for the fourth quarter of

calendar 2015. Initial production is planned

from a number of underground blocks that

PTM expects will soon be reached with

underground development. The largest

production ramp up area planned is from

‘Block 10’ and ‘Block 11’, using hybrid and

room and pillar mining methods respec-