Background Image
Previous Page  17 / 72 Next Page
Information
Show Menu
Previous Page 17 / 72 Next Page
Page Background

August 2015

MODERN MINING

15

MINING News

Hatch Goba designs Copperbelt mine shafts

The capability to design deep mine

shaft complexes, including ancillary

infrastructure such as underground

materials handling systems, has stood

Hatch Goba in good stead in complet-

ing a second major contract on the

Zambian Copperbelt.

Having successfully completed a

two-year detailed engineering design

project in 2013 for a 1 300-m deep

shaft (which comprised a shaft com-

plex with headgear, shaft steelwork,

winder house, underground materials

handling systems and a mine dewater-

ing pumping system), Hatch Goba was

subsequently awarded the detailed

engineering design for an expansion of

the same project.

Hatch Goba’s scope of work covers

two shafts, each about 2 000 m deep, to

allow the client to proceed with project

implementation. Hatch Goba Project

Manager Louis du Plessis states that

the aim is to access deeper parts of the

orebody and thereby reduce operating

costs.

“The detailed engineering design

of the two shaft complexes includes

the headgear, shaft steelwork, winder

house and underground materials han-

dling systems. Hatch Goba began work

in early 2013, with a projected comple-

tion date of June 2015 for the design

phase,” du Plessis comments.

“We were able to leverage off our

experience and incorporate it into

the expansion project, thereby saving

the client both time and engineering

design cost.” Hatch Goba has exten-

sive experience in this regard, having

designed numerous shaft complexes

over the years. “We have an excellent

track record, in addition to employing

highly skilled and competent people

in our Mining Business Unit,” du Plessis

confirms.

tively. The main north decline access is

approximately 60 m away from Block 11.

Mining access for both Block 10 and

Block 11 is scheduled for August 2015. On

the south mine, Block 16 is scheduled to

contribute to the ramp up phase.

Underground development and the

establishment of infrastructure towards

blocks that can benefit from mechanised

or partly mechanised hybrid mining has

been the focus for PTM and its contractors

over the past fewmonths. A conveyor from

1 423 m down the north decline to the ore

silo on surface and into the mill is expected

to be completed in October 2015. The

above ground portion of this conveyor has

now been completed.

The mill has been completed in accor-

dance with the original design and as

planned. The decision to add a MF-2 grind-

ing circuit on completed foundations,

thereby increasing capacity from 110 ktpm

up to a full 160 ktpm and take the mine up

to its planned 250 000 ounce 4E steady

state capacity, will be made as required

during 2017.