MODERN MINING

August 2015

MINING News

In its report for the three months ended

June 30, First QuantumMinerals (FQM) says

that its new smelter at the Kansanshi cop-

per mine in Zambia reached commercial

production status ahead of expectation.

During the six-month commission-

ing and ramp-up period, approximately

First Quantum reports on progress of Zambian projects

157 600 tonnes of copper concentrate

was processed consisting of a mixture

of stockpiled and fresh concentrate from

FQM’s Kansanshi mine and fresh con-

centrate from its new Sentinel mine in

north-west Zambia. Production totalled

46 700 tonnes of copper anode and

The Kansanshi smelter, which has now achieved commercial production (photo: FQM).

The Sentinel mine showing the stockpile area. Sentinel will have the capacity to produce up to 300 000 t/a of copper over a 15-year mine life (photo: FQM).

201 300 tonnes of sulphuric acid.

The smelter recorded throughput of

over 80 000 tonnes during the month of

June, representing 76 % of design capac-

ity, and smelter recovery rates were above

design rates in the same period.

Commissioning progress continued at