TÜV SÜD Product Service

Home Phases 1-5 Phases 6-16

8

Objectives

To develop a plan for the installation of the E/E/PE safety-related systems in a controlled manner,

to ensure that the required functional safety is achieved; To develop a plan for the commissioning

of the E/E/PE safety-related systems in a controlled manner, to ensure that the required functional

safety is achieved.

IEC 61508

Part 1 Clauses

7.9.1

7.9.2

IEC 62061

Clause 6.13.2.1 – A

SRECS shall be installed

in accordance with the

functional safety plan for

the final system

validation (clause 4.2.1

item (h))

ISO 13849

Not covered

Overall installation and commissioning planning