Table of Contents Table of Contents
Previous Page  608 / 975 Next Page
Information
Show Menu
Previous Page 608 / 975 Next Page
Page Background

3

Disclaimer:

The content in this paper is loosely based on experiences, and have been embellished to bring out the salient points

against the objectives of this paper.

As an end user does your company have or employ the organizations, processes and competences that

directly maps to Figure 1? Or as an end user does your company have or employ the organizations,

processes and competences that may map those in Figure 1?

Note the question did not focus on projects as Figure 1 covers all stages and life-cycle. For projects only

a few of the clauses are covered, typically clauses 5 through 15, but can include clauses 17 and 18. For

end users all clauses apply.

As an end user are all the clauses applicable to you?

Discussion

For Greenfield (e.g. a new site) the clauses 5 through 15 usually have more than one company,

organization or disciplines involved. That is the end user identifies the project requirement and may

contract out to an EPC (Engineering Procurement contractor) for the design and maybe another

contractor for the construction. As SIS is part of Functional Safety there are multi-disciplines involved in

these companies. There is also the equipment manufacturers’ who must meet the requirement

specification.

There are international standards such as IEC 61511, and others, and possibly end user company

standards.

All this provides multiple interfaces and information transfer that require to be managed. Back to the

football analogy, if the ball is not under your control and you try to pass it then it may not go where you

intended.

Whilst there are multiple interfaces and complexity for Greenfield projects these generally can be easily

managed for delivering Functional safety.

Modifications and decommissioning brings other challenges. Modifications can be from small changes to

Greenfield projects adding to Brownfield processes. It can also include elements of decommissioning

where the equipment for decommissioned functions is re-used with changed functionality.

Modifications has similar multiple interfaces, standards etc. as for Greenfield, but with added interfaces

and complexities with connections to the Brownfield equipment and from operational constraints.

The intent of the following case studies is to show where things can go wrong, and where it could be

said it was a team of individuals and not an individual team.

Case 1: Loss of containment detection from low pressure detection

Some international standards suggest the use of low pressure detection for the identification of loss of

containment from leaks.