![Show Menu](styles/mobile-menu.png)
![Page Background](./../common/page-substrates/page0346.jpg)
7
Disclaimer:
The content in this paper is loosely based on experiences, and have been embellished to bring out the salient points
against the objectives of this paper.
• All field devices are operational;
• Logic solver and input/outputs are operational;
• The interfaces to other systems and peripherals are operational.
The summary of this case study is that Greenfield / Brownfield:
1.
Design must include Functional safety assessment of designs to review all interfaces with
Brownfield systems.
2.
Installation, commissioning, and validation testing must include testing all interfaces with the
Brownfield systems, with activation of relevant shutdown levels.
Project 2: Modifications/ Decommissioning
During a routine process shutdown test only a small proportion of the process had shut down. The
process had to be manually shut down. The process was shut down for circa 3 days before the cause was
identified and rectified, which had a direct cost of in excess of £3M.
One year earlier the shutdown system had operated as required.
The initial site investigation identified modifications had been carried out on the system. All of which
had been installed and their functionality tested, and brought into service, and functionally operated as
per design.
Thus it appeared that cause of failure in the shutdown system was not from modification, and further
investigation into components started.
The further investigation added the technical authority and the system vendor to the team. The team
revisited each of the modification packs including the as built drawings.
One of the designed modification had to be changed during the implementation as the design assigned
input module had been used by another change. The installation used another input module that had
been previously decommissioned. This change to the design had been tested and the designed function
for this change had functioned as per design with the correct effects. No issues were found or evident,
however as was seen later this modification had a massive effect on the capabilities of the shutdown
system.
IEC 61511 Part 1 clauses 17 (Modifications) and 18 (Decommissioning) are very small in relationship to
the rest of the standard, but have clear messages about
approvals
and
safety integrity of the SIS is
maintained despite of any changes made to the SIS
.
The investigation identified that the decommissioned module had not been fully decommissioned as
wires had been left on the backplane. The modification for the new design that now used this module
added a 24V feed to one of the backplane pin, which in course tied the shutdown rail to a permanent