Previous Page  10 / 40 Next Page
Information
Show Menu
Previous Page 10 / 40 Next Page
Page Background

8

Mechanical Technology — February 2016

Special report

T

he idea underpinning large in-

tegrated modular plants arose

while Warwick Jackson was the

lead electrical engineer for Anglo

American – Kumba Iron Ore – SSP on

the development of its operations in the

Northern Cape. He had been told that it

was not feasible to build large substa-

tions offsite, because they could not fit

into standard ISO shipping containers,

making delivery impossible.

“After the meeting, I happened to

be driving behind a Komatsu 960 haul

truck. At 11,6 m wide, I realized that

products five times wider than conven-

tional ISO containers were being rou-

tinely delivered to sites all over Africa,”

Jackson says.

On discussing his observation with

his switchgear colleagues, Jackson was

advised to talk to Efficient Engineering.

“Johan Basson, who ran RBF at that

time, now JB Switchgear, recommended

Efficient, which, he said, was not afraid

of size,” he recalls.

“That is where my relationship with

Efficient began. I met Tony Cimato, the

then owner, who showed us how the

company made large buildings, control

rooms and huge shell structures to house

equipment: for shiploaders, e-houses,

and reclaimers, for example,” he adds.

For Kolomela, Efficient Engineering

was willing to build the shells for the sub-

stations, motor control centres (MCCs)

and control and instrumentation (C&I)

rooms as single integrated modules, and

fully equip them offsite. “So my staff and

I were given an office here at Efficient,

where we collaborated to build exactly

what we needed for Kolomela. It was a

fantastic way of working,” Jackson says.

The result was the development of

seven ‘buildings’ that met the project

requirements for the entire electrical

infrastructure needed at Kolomela: for

A revolutionary offsite approach

to plant projects

Following the successful deployment of seven modular ‘buildings’ for the electrical

infrastructure at the Kolomela mine, Efficient Engineering has pioneered the offsite

construction, assembly, testing and commissioning of complete modular plants

similar to as these, which include the containment structures and all functional

equipment.

MechTech

talks to Warwick Jackson (right), now the managing

director of Efficient Power and the inspiration behind this new approach.

the primary, secondary and tertiary

crushers; the run-of-mine conveyor; the

product screen; the load out station; and

the dewatering pump station.

“It was an amazing success. The

modular plants arrived on site 100%

commissioned. Our slogan was from

motor to mouse. Only once everything

was signed off at Efficient Engineering,

did we arrange delivery to site. Once

there, we connected the power cables

and everything worked,” he says.

On the Kolomela project, Anglo had

a R500-million budget for the electrical

and C&I infrastructure. For the seven

substations, the building budget was

R11‑million. “By taking the offsite modu-

lar approach, the shell structures cost

close to R15-million, but by the time we

had completed the installation, we had

under spent our R500-million electrical

budget by R83-million,” Jackson says.

So by agreeing to spend R4-million