Previous Page  11 / 40 Next Page
Information
Show Menu
Previous Page 11 / 40 Next Page
Page Background

Mechanical Technology — February 2016

9

Special report

Above:

Based on its success at Kolomela, Efficient

Engineering now builds fully functional e-houses, includ-

ing the shells for the substations, motor control centres

(MCCs) and control and instrumentation (C&I) rooms as

single integrated modules, and fully equips them offsite.

Left:

A modular pump station was built by Efficient Power

to pump and additional 1 800 m

3

/h at a 40 m head from

the deepening pit.

Centre:

To accommodate pumps, decoupling vibration

dampers and reinforced mountings carry the 35 t of trust

down to the 3.0 t concrete mounting plinth below the

‘building’. Shuttering formwork and a steel reinforcement

cage was also incorporated below each pump.

Below:

Built into the housing structure is an overhead

crane to enable installation and servicing of the heavy

pumps and piping systems.

extra on the offsite modular construction

approach, R79-million was saved.

The main reason? “The provisional

and general budget virtually disappeared,

because all the work was done offsite.

Very few contactors had to be paid

for travel, accommodation or material

shipping costs to the site. In addition,

the contingency budget went unspent,

because there were no unexpected ad-

ditional costs due to onsite issues.

“And the knock on savings were outra-

geous. We closed a site with running costs

of R150-million per month five months

early. As a result, 1.4-million tons of ore

was put through the mine before it was

due to open – and the capital expenditure

for the development of Kolomela, which

was about R8.4‑billion, was paid off in

24 months,” Jackson reveals.

From electrical to mechanical

plant

Pit dewatering at Kolomela is achieved

via 16 boreholes that lower the surround-

ing water table. “The water is fed into

an eight-million litre water tank and it

is then pumped 18 km as potable water

to Beeshoek, into the Vaal Gamagara

municipal intake at up to 1 500 m

3

/h.

“While the mine had moved towards

offsite modular designs with respect to its

substations and MCCs, the pump house

itself experienced civil delays. We had a

fully functional MCC control room and

all of the medium-voltage infrastructure

onsite and operational, but the pump sta-

tion building hadn’t been completed. So,

while massively successful on the electri-

cal side, we were still being hampered by

delays on the civil and mechanical side,”

Jackson says, adding, “the budget for the

pump station building was originally in

the order of R1.8-million, but it ended up

costing well north of R4-million – and it

was more than eight months late.”

“Onsite construction of plant at re-

mote mines is such an onerous thing. A

project can be hampered by continuous

delays, due to late deliveries of inputs,

the wrong people being sent to site and

a host of safety and security restrictions

that make rapid progress impossible,”

he explains.

Following the success of Kolomela