Previous Page  8 / 64 Next Page
Information
Show Menu
Previous Page 8 / 64 Next Page
Page Background

6

MODERN MINING

August 2017

MINING News

In its second quarter report (to 30 June

2017), ASX-listed Syrah Resources says

that its Balama graphite project in north-

ern Mozambique was 90 % complete at

the end of the quarter with commissioning

activities underway.

It notes, however, that subsequent

delays in the construction completion of

the processing plant have led to a delay

in the commencement of production

from late August into October and to

an increase in the construction budget

(including contingency) to US$205 million

from US$200 million.

According to Syrah, the slower than

planned completion of structural steel

erection, piping installation and electrical

work in the processing plant (particularly

in the flotation and filtration areas) can

be attributed to a number of factors,

including contractor productivity and

commitment to scheduled completion

dates. It also cites some specific material

shortages of vendor-related equipment

and piping materials, minor fabrication,

design and installation issues, requiring

re-work, and reduced power availability

delaying commissioning.

Commissioning activities began in

May 2017 utilising low voltage generator

capacity on site and the planned usage of

a 1 000 kVA portable generator from early

July. On-site commissioning of the power

station was dependent on the use of a load

bank and sufficient load being available

from the processing plant. Unfortunately,

says Syrah, a truck transporting both the

generator and the load bank was involved

First production from Balama delayed till October

The Balama processing plant photographed in June this year (photo: Syrah Resources).

in an accident en route from South Africa

resulting in both items needing to be

replaced. The replacement load bank and

generator arrived on site at the end of July

and have now been installed.

Syrah says that management and

supervision continue to give the highest

priority to recovering lost time and have

been working around the clock with con-

tractors to implement several initiatives to

ensure delivery of the project. The com-

pany notes that, as the delay is relatively

short and the initial planned production

volumes are modest, it does not antici-

pate any material impact on total planned

production for the 12-month period com-

mencing August.

The operations team organisational

structure is established and staffed, and

the teams are completing training and

preparation for operation of the pro-

cessing plant. The mining contractor is

established and – says Syrah – displaying

excellent operational performance with

initial mine development and the stock-

piling of mineralised ore onto the ROM

stockpile complete, ready for production.

The mining technical support team con-

tinues to refine the mine planning model.

Balama will be a simple, low strip ratio,

open-pit operation. Processing will utilise

conventional processes including crush-

ing, grinding, flotation, filtration, drying,

screening and bagging. The processing

rate is 2 Mt/a with the nameplate capacity

being 380 000 tonnes of graphite concen-

trate per annum.

Ity indicated resource climbs by a million ounces

Endeavour Mining, listed on the TSX,

reports that its exploration programme

at its Ity CIL project in Côte d’Ivoire has

increased the indicated resource by 1,0 Moz

to 3,8 Moz since the beginning of the year.

This marks a 1,5 million ounce increase

in the indicated resource base since

the publication of the November 2016

Feasibility Study (FS), representing a 65 %

increase. An updated reserve estimate

is due to be published in September

as part of an Optimisation Study (OS)

which is expected to be based on a circa

4,0 Mt/a gravity circuit/CIL plant, an

increase from the previously contemplated

3,0 Mt/a plant, to better capture the value

created from recent exploration success.

“Our exploration team has done excep-

tional work over the past months which has

led to a significant increase in the resource

base at Ity ahead of the Optimisation Study,”

commented Patrick Bouisset, Executive

Vice-President Exploration and Growth at

Endeavour. “These results and the numer-

ous other identified targets, on which

initial drilling reconnaissance is currently

being conducted, further demonstrate the

prospective nature of the greater Ity area

and our confidence in delivering against

our five-year exploration strategy disclosed

last November. We believe that the 80 km

Ity corridor which we control is among the

most prospective areas in West Africa and

we look forward to building on our explora-

tion success.”

Sébastien de Montessus, President and

CEO, stated: “Under Patrick’s leadership,

Ity has been transformed from a 20-year

operation nearing the end of its life into

an asset that now has the potential to be

one of our flagship operations. Our abil-

ity to quickly grow the indicated resource

demonstrates the robustness of Ity, as well

as the quality of our exploration team.

We now look forward to announcing the

results of the Optimisation Study and

making a formal investment decision in

September, following which we will transi-

tion the construction team fromHoundé to

Ity later this year.”