To date, 15 people from the Construction Services business line have

participated in the completed projects, as well as projects currently

underway. AECOM’s first task order, from 1 July 2014 to 31 March

2016, was completed on time for the start of the 2016 academic year,

and within the cumulative budget of about R750-million for the first

three building projects and associated infrastructure. The value of the

total programme, comprising all projects completed to date, as well as

projects currently underway, is approximately R1,5-billion.

The team earned high praise from the client, with AECOM receiving

an extension of its contract up to May 2018. “This is testimony to the

client’s satisfaction and faith in the AECOM team,” De Koker comments.

“AECOM team’s commitment, effort and drive contributed to the

overall success of this project as it enabled design challenges to be

overcome; getting consultants to commit; being able to assist with

the contractors’ commitments to deliver; managing socio-economic

commitments in a difficult environment; and overall professional

conduct. This is while always placing the interests of the programme

first, particularly with a challenging NEC target-cost framework contract,”

De Koker elaborates.

The team received a ‘Very

Good’ Safety rating on the

project, with no serious injuries

reported to date. AECOM

utilised its LifeGuard reporting

system, which allows anyone

on-site to log an occurrence

or incident on-line, with an

accompanying photograph and

any background information.

The relevant contractor is then

notified and the incident is only

removed from the LifeGuard

reporting system once it has

been resolved.

On track at Sol Plaatje

University in Kimberley

In May 2014, the University of Witwatersrand appointed

AECOM to provide project-management services relating

to the development of the Sol Plaatje University precinct in

Kimberley. Over the past two and a half years, the team has

been under the leadership of Don de Koker, Bradley Marais

and Toni Capuzzimati.

AECOM was appointed to provide project management services relating

to the development of the Sol Plaatje University.