Previous Page  38 / 68 Next Page
Information
Show Menu
Previous Page 38 / 68 Next Page
Page Background

CONSTRUCTION WORLD

APRIL

2017

36

GEOTECHNICAL ENGINEERING

While there has been some local adoption

of horizontal directional drilling (HDD) in

small bore applications, with holes measure

less than 500 mm in diameter, South Africa

has not realised the potential of large bore

HDD, according to LR Civil operations

manager, Daniele Carnicelli.

Partnering with geotechnical engineers,

Geopractica and HDD experts TRG Inter-

national, LR Civil recently completed

an HDPE pipeline a kilometre long under

a Port Alfred beach and out to sea. “This

contract demonstrated a number of benefits

that this technology has to offer in South

Africa, including little or no environmental

impact, much less time spent on permits

and approvals, and no disruption or danger

to the public,” says Carnicelli.

The project

Drilling horizontally at depths of between

20 and 30 metres, the 150 tonne Maxi-

Rig drilled the outfall pipeline for the new

reverse osmosis desalination plant at Port

Alfred, without any threat to the pristine

beach environment.

“With the capacity to install pipelines of

up to 900 mm in diameter, this powerful rig

has a maximum torque of some 70 tonnes

and 150 tonnes of pull-back force,” he says.

“This makes it capable of working through

rock with a hardness exceeding 250 MPa,

and to achieve daily horizontal distances

well in excess of conventional trenching.”

He estimates that, on the desalination

plant project, the rig could achieve a

horizontal distance of at least 30 metres on

an average day and 45 metres on a good

day. With traditional trenching, involving

digging, laying, backfilling and perhaps even

blasting, such daily rates could take a week

or more to achieve.

Not having to dig from surface to lay

and bury large diameter pipes means that

many of the normal challenges of pipeline

installation are sidestepped altogether.

Where a pipeline crosses a watercourse,

for example, a water use licence may be

required. This a process could take up to

18 to 24 months and possibly delay a

project significantly.

Other permissions usually need to be

secured wherever a trench will intersect a

gas, power, telecommunications or water

line. In the case of HDD, the drill path simply

goes under these facilities and safely

avoids them.

Safety risks on a project are reduced,

as the absence of trenches means less

danger to workers and the public. Inclement

weather, which can often threaten the

timeline of a project by flooding trenches

and stopping construction work, is no

longer a factor, as most of the activity in an

HDD project is carried out underground.

Fuel consumption

Fuel consumption is vastly reduced, as

comparisons show that the Maxi-Rig will

tend to use as little as 5% of the diesel

normally consumed by earthmoving

equipment, including excavators and trucks,

over the life of a project.

According to Carnicelli, there are

also substantial savings in reducing the

pipeline length by installing it ‘as the crow

flies’ through a horizontal drill hole, rather

than the more circuitous route required

by trenches which have to avoid objects,

With 30 years of experience laying pipelines for the civil engineering

sector, Raubex Group company LR Civil and its partners have imported

a well-established technology for unobtrusively installing large bore

pipelines – proving its value on South African soil.

LESS TIME, COST AND DISRUPTION

for large-bore pipelines

The 24 ton Maxi-Rig with the

control tower in view.

The rig drilling 650 metres under existing

sand dunes towards the connection point.

Differential in heights is 60 metres from the

rig position to the connection point.

I

I