Previous Page  48 / 72 Next Page
Information
Show Menu
Previous Page 48 / 72 Next Page
Page Background

46

CONSTRUCTION WORLD

APRIL

2016

GEOTECHNICAL ENGINEERING

In February 2015, the CTICC East

contract was awarded to Franki

Africa by Aveng Grinaker-LTA

Building Cape, following on from

the basement lateral support for the first

phase of the CTICC extension which had been

successfully completed in 2014, with WBHO as

the main contractor.

The CTICC East contract consists of lateral

support in the form of Continuous Flight

Auger (CFA) piles with gunited arches for the

underpass, connecting to the existing CTICC,

together with piling for the access ramp from

the basement, which required piled lateral

support and anchors.

Jet grouting gravity wall

However, Franki Cape Town’s Anton Stoll

points out that conventional lateral support

could not be installed everywhere due to the

highly sensitive service lines feeding the city

centre and overpass headroom restrictions.

“In order to create the necessary lateral

support under this major servitude of cables,

a jet grouting gravity wall was considered to

be the safest solution, with the lowest risk of

damaging these vital services,” he says.

He adds that the existence of all the

electrical cables, water ducts and optic fibres

feeding Cape Town posed the greatest chal-

lenge on this project.

“These lines were so closely laid that

piling between them for lateral support was

just not possible. However, jet grouting allows

the installation of soil cement columns (with

diameters of up to 3,5 m) through a small

diameter borehole of less than 200 mm,

which makes this technology exceptional for

>

CTICC

EXTENSION

Maintaining its global competitiveness relative to

other international convention venues, the Cape

Town International Convention Centre (CTICC), which

has reached its capacity, needed to make structural

enhancements. The extension plans were announced

in 2013. Franki Africa was contracted to implement a

range of geotechnical works in various phases.

working around utilities without having to

disrupt their operations,” he says.

With the aid of high pressure cutting

jets, the soil around the borehole is eroded,

rearranged and mixed with the grout. The

columns can then be arranged and combined

in any way to form each type of element.

All service lines had to be identified and

completely exposed beforehand, and to

prevent possible damage during the instal-

lation of the jet grouting columns, they were

wrapped and encased in wooden boxes.

Franki Africa recommended that tempo-

rary 165 mm diameter ducts be installed to

guide the jet grouting process and protect the

service lines during drilling and jetting. These

sleeves were placed at a minimum depth of

500 mm below the service lines.

Thereafter, the exposed lines were

backfilled and compacted up to the existing

ground level to create access for the jet grout

rig. After all the preparatory work, the instal-

lation of the gravity wall could start with the

execution of three test columns to verify the

pre-determined jetting parameters.

“Thanks to the additional support from

Ralf Junker, a highly-experienced super-

visor from Keller Germany, we were able

to complete the trial phase and prove the

maximum required column diameter of

2 600 mm, after which the actual execution

of the gravity wall could begin,” Stoll says.

The drilling rod was guided within the

sleeves and overlapping columns were plotted

and set out to create a mass gravity wall below

the service lines.

During the process, a soil-cement mix

(sludge) was partly flushed out to the top

TOP TO BOTTOM:

Installation of the sleeves to protect services

from damage.

Layout of jet grouting columns.

Exposed trial column with a diameter of 2 600 mm.

The different sequences of the jet grouting process.

Boxed services suspended between the gravity walls awaiting slab construction.

of the borehole through the annular space

between the jet grouting rods.

Stoll says that pumping the sludge to a

temporary storage facility and then disposing

of it always poses a challenge, especially

when working in areas with restricted space.

“Sludge management is often crucial for a

successful jet grouting site, as it can dictate

the production rate. This also applied to the

CTICC project. However, after two weeks we

managed to complete the two gravity walls,

on which a slab could be cast, as well as span-

ning the walls and forming the roof of the exit

and entry ramps on which the service lines

could be supported,” he concluded.

The entire contract consists of piling, jet

grouting and lateral support, which include

oscillator piles for future developments, CFA

soldier pile walls, a Berlin Wall for temporary

support and bored piles for cranes.

I

I