48
CONSTRUCTION WORLD
APRIL
2016
GEOTECHNICAL ENGINEERING
Kobus Geyer, site manager for
Gauteng Piling, says the contract
for the piling – required to erect
a new five-storey parkade on the
tarred open-air parking area on the north-
eastern wing of the shopping mall – produced
formidable challenges right from the outset.
“We almost Immediately encountered
shallow, very hard rock which was to take
a heavy toll on our piling rigs and delay the
completion of the contract. In fact, as soon
as drilling commenced, we knew that the
stipulated piling depths were just not going to
be feasible.
So Gauteng Piling had to commission
geological tests of the soil bearing capacity to
obtain an indication of the the depth of the
rock and, based on the results of the tests, it
was decided that 59 holes that we had already
drilled had to be converted into mass rein-
forced concrete bases which, basically, is the
only solution when the ground bearing strata is
too deep for traditional piling,” Geyer states.
Because of the varying rock bearing
strength and depths, it was also decided that
the number of piles Gauteng Piling had to
provide had to be reduced from 160 to 42. But
more problems emerged.
“Once these piles were drilled, it was
discovered that the bearing capacity of the
rock varied from hole to hole. So, to overcome
this, smaller flights were used to re-drill all
the holes to refusal, i.e. as deep as possible.
A rock core barrel was then used to trim the
harder rock to the same level. Needless to
say, all of these special measures proved
extremely time-consuming and frustrating,”
Geyer added.
The piling operations took place on a 10
950 square metres area with most of the piles
PUSHED
to the
LIMIT
MBA North member, Gauteng Piling, had to resort to
exceptionally rare measures to cope with extreme rocky
terrain encountered while providing the auger piling
foundations for the expansion of the Fourways Mall
shopping centre, north of Johannesburg.
>
Established 20 years ago, Master Building
Association (MBA) North member Gauteng
Piling, has already completed over 1 500 major
piling projects in many parts of South Africa.
Included in prestige contracts handled was the
piling for the construction of Southern Afri-
can’s largest single-phase retail centre, Mall
of Africa, now under construction in Midrand,
which called for over 500 piles.
Other recent contracts handled by
Gauteng Piling include the piling for the
massive Value Logistics warehouse in Kempton
Park, the Fire & Ice Hotel in Pretoria, The
Grove Shopping Centre in Pretoria, and the
Bon Accord Police Station, also in Pretoria. The
company also handled the piling requirements
for a new FAW auto dealership in Croydon in
Ekurhuleni, as well as the piling for exten-
sions to the Market Theatre complex in the
Johannesburg CBD as well as the I’langa Mall
in Mbombela (Nelspruit).
3,7 metres deep, and the diameter of
the holes varying between 1 200 mm and
1 600 mm. The steel reinforcement cages for
the piles varied between 1 050 and 1 450 mm
in diameter.
Mota-Engil SA Construction are the
main contractors for the erection of the
parkade, but Gauteng Piling secured the
contract following a direct appoinment by
SIP Project Managers. The project started in
September 2015 and was completed in about
three months. Two piling rigs were initially
employed but, as site problems began to
mount, the fleet had to be expanded to four:
Hendrickson 80 and 120 diggers, an IMT
digger, and RTSA Soilmec unit.
Pictured at the start of piling operations for the extension of
Fourways Mall – a project that struck soil so rocky that exceptional
measures had to be employed.
I
I