Table of Contents Table of Contents
Previous Page  32 / 56 Next Page
Information
Show Menu
Previous Page 32 / 56 Next Page
Page Background

32

|

BIOFORE

working at the mill for some time after

the installation of PM1.

“Inmany ways, these two projects

have been similar but there are also

differences,” says Masterson. “For

example, this time much of our

equipment has been sourced from

China, while before almost everything

was imported. However, the biggest

difference – and challenge – has been

the swing-concept machine. Both the

machinery and the process itself have to

be flexible so that we canmake quick and

effective grade changes. For example,

the machinery has to be completely

cleaned and reset for the next product.

“This has not only been a big

challenge for the project team; it will

also be a big challenge for the mill’s

operators as they take over,” says

Masterson.

Finnish consultancy Pöyry and

Chinese design institute Haisumwere

chosen as the engineering companies.

Voith of Germany was selected as the

supplier for the new paper machine.

This marks the first time that UPM

bought a machine of this size fromVoith.

“We were very happy to be selected

for this UPM contract. This has been

a big and demanding project, because

the machine will be producing different

kinds of paper grades,” says

Johannes

Rimpf

, Voith’s Project Manager for the

PM3 project.

On-site installation of the machine

started inMay 2015, after which Voith

worked closely with UPM’s project

teamuntil early December, when

the machine was handed over to the

Changshumill.

“It has been a high quality project

all over, especially in terms of safety,”

says

Wolfgang Windisch

, Installation

Manager at Voith. “The regulations are

strict and the safety targets are always

followed up. I believe that UPM’s

‘Finnish touch’ has contributed to the

project’s success on the safety front.”

Tight schedule

Even though the schedule was tight,

UPM’s project teamplanned the project

so thoroughly that there were no severe

delays.

The project commenced with the

construction of roads, buildings and

other engineering.

Nantong Construction Group

(NTCC) of China was selected as the

general construction contractor.

Nantong and UPM go way back, as

Nantong was also involved in the

construction of the PM1 project from

2003 to2005. All of the subcontractors

were selected by UPMand are mainly

local companies.

“We managed to stick to the

schedule despite the fact that we had

many more rainy days than expected.

During 2014 we lost 38 days due to

rain, forcing us to stop all construction

work for safety reasons and due to

difficult working conditions,” says

Antti Mankki

, Project Construction

Manager.

“This was the first time

we’ve completed a project in

China involving so many local

suppliers and engineers.

It has been a very positive

experience for me.”

Timo Heinonen,

PM3 Project Director

People concentrated in the control room.

Timo Heinonen