Total Site Solutions Mobilisation Guide

Total Site Solutions (TSS), part of Murphy Plant, strives to be an industry leader and innovator in the planning and delivery of site mobilisations. By integrating our UK-wide expertise and our broad range of functions, we offer a one stop solution for our projects. The one stop approach standardises the set up of sites, and aligns with our Ten Year Plan by mobilising new projects brilliantly – always right first time. When you contact the TSS team, you will be greeted by our expert advisors who will guide you through the process. TSS will handle the entire set-up schedule, including planning, delivery, installation, IT, communications and utilities. Following initial planning, our scheduled set-up process will ensure everything runs smoothly, while we pro-actively support project teams to deliver sites efficiently and on time.

TOTAL SITE SOLUTIONS MOBILISATION GUIDE

JULY 2017

CONTENTS

Our mission statement Total Site Solutions offers a complete, planned and structured approach to site accommodation. Our goal is to deliver the highest quality service and a professional work environment for everyone.

■ Our team values are integrity, honesty, openness and mutual respect. ■ We provide the highest quality service and are passionate about innovation to improve the design of our cabins. ■ People are key to our on-going success and we invest in their training, development and welfare. ■ We operate in a sustainable way; opportunity is taken to reduce waste and we constantly look at how we can improve the efficiency of our products.

MURPHY PLANT TOTAL SITE SOLUTIONS

Total Site Solutions (TSS), part of Murphy Plant, strives to be an industry leader and innovator in the planning and delivery of site mobilisations. By integrating our UK-wide expertise and our broad range of functions, we offer a one stop solution for our projects. The one stop approach standardises the set up of sites, and aligns with our Ten Year Plan by mobilising new projects brilliantly – always right first time. When you contact the TSS team, you will be greeted by our expert advisors who will guide you through the process. TSS will handle the entire set-up schedule, including planning, delivery, installation, IT, communications and utilities. Following initial planning, our scheduled set-up process will ensure everything runs smoothly, while we pro-actively support project teams to deliver sites efficiently and on time.

About us

1 3 5 7 9

Accreditations

Safety

Never Harm Culture

Culture Development Programme

Compliance and innovation

11 11 15 18 20 23 25 31 37 41 43 45 47 49 51 52 54 56

Nationwide coverage

Environment and sustainabilty

Mobilisation start point

The process

Requisition time-line

Major, modular sites and scaleable solutions 50+ people

Large projects 21 - 50 people Medium projects 11 - 20 people Small projects 1 - 10 people

Optional extras

Communication (IT and telephony)

Electrical systems

Water and waste management

Fire systems

Security systems

Logistics

Meet the team / contact information

Total Site Solutions | www.murphygroup.co.uk

ABOUT US

1

ABOUT US

In order to deliver a ‘right first time’ approach, Total Site Solutions has developed this guide to provide information on: ■ First point planning (tender stage) ■ Project management (site planning) ■ Process map (ordering time-line) ■ Standard site set-ups ■ Modular accommodation ■ IT and telephone installation ■ Electrical installations ■ Method and risk assessments ■ Logistics ■ Waste management ■ Security ■ Utility connections ■ Fire regulations

Planning these functions into an agreed programme of works, in an agreed time-frame, will ensure that sites are delivered on time and fully operational.

2

Total Site Solutions | www.murphygroup.co.uk

Total Site Solutions work in partnership with our supply chain partners to provide efficient, cost effective site accommodation. They hold the following accreditations:

3

ABOUT US

Murphy Plant is committed to self-improvement and best practice. We hold various industry-standard accreditations and memberships, including gold status from the Fleet Operator Recognition Scheme (FORS) run by Transport for London.

Van Excellence is an industry-led initiative that aims to: ■ enhance standards of van operator compliance ■ celebrate operators who demonstrate excellence ■ represent the interests of the van industry ■ increase safety for your drivers and other road users ■ obtain recognition from the industry, customers and the public for the highest operating standards ■ gain peace of mind in the legal compliance of your van fleet. The Fleet Operator Recognition Scheme (FORS) is a voluntary accreditation scheme that promotes best practice for commercial vehicle operators. With over 4,250 members, FORS is gaining recognition as the transport industry’s go-to accreditation scheme. FORS encompasses all aspects of safety, efficiency, and environmental protection by encouraging and training fleet operators to measure, monitor and improve performance. FORS provides accreditation pathways for operators of any type, and for those organisations that award contracts and specify transport. requirements. V CLOCS brings the construction industry together to revolutionise the management of work related road risk (WRRR) and ensure a road safety culture is embedded across the industry. By working together we can help protect pedestrians, cyclists, motorcyclists and other road users who share the roads with construction vehicles. The Construction Plant-hire Association (CPA) is the leading trade association for this sector in the UK and CPA members supply 85% of hired plant to the construction industry. Established for 75 years, the CPA has over 1,600 members and is governed by a council of members, who represent plant-hire companies of all types and sizes throughout the country.

4

Total Site Solutions | www.murphygroup.co.uk

SAFETY

5

SAFETY

Total Site Solutions is committed to high standards of health and safety. We continually work to eliminate risk, providing a safe and compliant service. People are our most important asset and we provide safe and healthy working conditions for our employees, both direct and those self-employed. We also ensure that our work does not endanger anyone, including members of the public. By working with key suppliers and our own Safety, Health, Environment, Sustainability and Quality team (SHESQ), we have developed an offering that makes us the premier service for delivering your site. Key safety initiatives ■ Low level lifting points on accommodation units ■ Fork lift tunnels in all newly supplied accommodation units ■ PAT tested appliances ■ Heat deflectors for convectors

■ Temperature controlled water heaters ■ Comprehensively trained operatives ■ Stay backs supplied to store doors ■ Door closers for heavy doors Defibrillators and first aid equipment The wellbeing of Murphy staff is vitally important. We treat provision of first-class emergency equipment as fundamental to their welfare and achieving the high standards of health and safety we expect on our sites. Sudden Cardiac Arrest (SCA) is one of the biggest causes of death in the UK; over 60,000 people a year (which include 12 young people per week) die as a result of a SCA. 12,000 SCAs occur at work or in a public place.* In order to administer rapid treatment, TSS makes sure every site has access to a portable defibrillator.

All sites are supplied with the appropriate amount of first aid equipment and other supplies for the size of the site and number of personnel. Consensus Paper on Out-of-Hospital Cardiac Arrest in England; Resuscitation Council (UK) 16th October 2015 *

6

Total Site Solutions | www.murphygroup.co.uk

NEVER HARM VALUE

Murphy is a leading multi-disciplined engineering and construction company which delivers safe, innovative and sustainable solutions to the most complex infrastructure problems. Murphy’s vision is to create a sustainable future through delivery of world-class infrastructure. Never harming people, the environment or communities is a core value to Murphy. The company believes that regardless of the quality of safety systems, it is the strength of the safety

culture within an organisation that determines how closely it can achieve this. And even then, the real key is sustaining it. Murphy recognises that excellence is achieved by making safety its core value for each employee. Acknowledging that one-hit safety training does not achieve sustainability, Murphy has a Culture Development Programme to deliver it’s never harm goal.

7

OUR NEVER HARM VALUE

One of Murphy’s company values is to never harm. Murphy’s mental tools help employees understand the triggers of their actions and empowers them to make safer choices. They are: ALPHA Good housekeeping will keep you safe in this daydreaming state, because you are not aware of your surroundings. HABITS Habits can be either good or bad. Forming good housekeeping habits will keep you safe whilst in Alpha. TIME VS. RISK (TVR) Time is our most precious commodity. Ask yourself, is the shortcut you might take worth the time you will save? e shortcut really worth the 5 minutes you will save? RISK TIME

PERSONAL RISK PERCEPTION (PRP) We never see ourselves having an incident. Do you see the risks you are taking though?

COMMUNICATION Talk to people about our values and mental tools.

8

Total Site Solutions | www.murphygroup.co.uk

CULTURE DEVELOPMENT PROGRAMME

C

M

Y

CM

MY

CY

CMY

K

Living the ‘One Murphy’ value means engaging with our people, promoting best practice, continuously improving and innovating in everything we do. To encourage everyone to participate, we have card stations and white boards in all of our canteens for staff to submit feedback and ideas.

The culture development team reviews all of the cards submitted and ensures they are acted on and replied to swiftly. This constant dialogue helps us improve our work environment and find new, better ways of working. Our goal is to set industry standards with truly world-class projects and sites.

Our m Do our feedb Can thin wor

24/05/2017 15:46:23

CDP card station

ur Murphy values Our values shape everything we do. When filling out CDP cards, consider how our values have been demonstrated positively, or how we could improve.

We want your feedback Our cards can be used to give feedback and share ideas across the company. Every comment you make will be considered seriously and appropriate actions taken. What’s more we will always provide a response to the information you provide within four weeks. The group-wide process is shown below and illustrates how your feedback will be dealt with. We are always pleased to hear about anything you wish to raise. This could be something to do with values, positives, challenges, improvements or recognition.

Start

Simply take a card, fill it in and follow the process below.

Whatdo youwant to tellus?

Always Deliver

A ‘can do’ attitude achieves excellent productivity and delivers high quality projects on time and on budget.

no

Is iturgent/ reportable incident?

Blank feedback cards

yes

Speak to your line manageras soonas possibleanduse2-1-2

Never Harm

We look after people, their communities and the planet — no matter what.

FilloutaCDPcard

Does the card include confidential/sensitive information?

Integrity & Respect

CDP CARD

Yournominatedperson will fill in the ‘action taken’ sectionon yourcard

yes

no

Transparent, honest, inclusive and professional, embracing diversity — we act with integrity and our stakeholders trust us.

Thenominatedperson willupdate ‘You said, Wedid’boardeveryweek.

Speak to yourmanager first,whowill listenand act if required.Pass your card to themor your designatedperson. Thismay thenbediscussed at thenextCDP forum.

Thenominatedperson willenter thecard information into theCDP feedback systemon the Intranet

Alpha

Constantly Improve Innovation is integral to our success.

Always Deliver

Time vs Risk

RISK

TIME

9

Habits

Never Harm

H A B I T S

Hasan actionor response beenagreedand fedback to you?

Choose from these options: Call Care first 0800 174 319 whocanbe found

no

PRP

y

Contact theCDP team at feedback@murphygroup.co.uk orcall theCultureandengagement ministrator inLeeds 0611

Integrity & Respect

yes

ts a seamless,

You said

We did

A3

Team commitments

1

2

Feedback dashboard

3

4

5

6

7

Teamsignatures

A ‘cando’attitudeachievesexcellentproductivityanddelivershighquality projectson timeandonbudget.

Goodhousekeepingwillkeep you safe in thisdaydreaming state,because youarenotawareof your surroundings.

We lookafterpeople, their communitiesand theplanet—nomatterwhat.

Time isourmostprecious commodity. Ask yourself, is the shortcut youmight takeworth the time youwill save.

Transparent,honest, inclusiveandprofessional,embracingdiversity — weactwith integrityandour stakeholders trustus.

Habits canbeeithergoodorbad. Forminggoodhousekeepinghabitswillkeep you safewhilst inAlpha.

Wenever seeourselveshavingan incident. Do you see the risks youare taking though?

Collaborativeworkinggivesour clientsa seamless, integrated service.

TIME

RISK

H A B I T S

Talk topeopleaboutour valuesandmental tools. Fill inaCDP card to share your ideas.

www.murphygroup.co.uk

ntal tools mental tools apply to your ck? ou suggest ways to improve s by applying them in your environment?

CDP CARD

FEEDBACKCARD_CDPMay27Final.pdf 1 23/05/2017 13:54:41

Alpha

Alpha Good housekeeping will keep you safe in this daydreaming state, because you are not aware of your surroundings.

Time vs, Risk

Always Deliver

RISK

TIME

Habits

Never Harm

H A B I T S

Time vs, Risk

PRP

Time is our most precious commodity. Ask yourself, is the shortcut you might take worth the time you will save.

RISK

IME

C

Integrity & Respect

M

Communications

Y

Habits

Constantly Improve One Murphy

H A B I T S

CM

Habits can be either good or bad. Forming good housekeeping habits will keep you safe whilst in Alpha.

MY

CY

Manager

CMY

PRP We never see ourselves having an incident. Do you see the risks you are taking though?

Client

Supervisor

K

ARE YOU:

Subcontractor

Operative Leader

Communication Talk to people about our values and mental tools. Fill in a CDP card to share your ideas.

Contact us feedback@murphygroup.co.uk Culture and engagement administrator: 35 0611

10

Total Site Solutions | www.murphygroup.co.uk

COMPLIANCE AND INNOVATION

New integrated eco-specification ■ Double glazed windows that improve U-Values through better insulation ■ Blinds to reduce sun glare ■ Passive infra-red (PIR) sensors to operate lighting ■ Thermostat / timer controlled heating system ■ Air conditioning to allow doors and windows to be closed and create a comfortable working environment ■ Heavy duty door closers to retain heat ■ Dual flush cisterns and non-concussive push taps to reduce water consumption ■ Sustainably sourced timber ■ Insulated window shutters and external doors

Innovation With a strong culture of innovation, Murphy encourages its employees to think freely and creatively to provide safe and sustainable solutions to complex infrastructure problems. We recognise innovation is the key to delivering safer, smarter and greener solutions for clients. We offer a variety of different upgrades to our anti-vandal units which provide both economic and environmental benefits: ■ Insulated floors (PIY / foam / PIY) (underdrawn) – help regulate temperature by minimising heat loss and insulating against the cold ■ UPVC windows / doors (double glazed) – insulated windows and doors add environmental and cost benefits by reducing heat loss ■ Door closers – closed doors reduce heat loss and save energy

11

CONTINUOUS IMPROVEMENT Innovation is integral to our success and we look to make improvements in all aspects of our work.

■ Waterless urinals – reduce water use and improve sustainability ■ Non concussive taps – taps cannot be accidentally left on, saving water ■ PIR controls – lights come on automatically when someone is in the room, turning off once they leave. This saves electricity and reduces energy costs ■ LED lights – LED lights are highly efficient and have an outstanding operational lifespan ■ Timed heating systems – energy is saved by only providing heat when it is required. ■ AC inverters – AC inverters store energy, reducing live energy requirements when electrical goods are switched on. All of these contribute to more energy efficient buildings. Our supply partner can calculate the EPC rating of a building and advise on ways to improve this.

EPC ratings depend upon the site, location and factors such as the country the building will be in. The more the rating goes up, the more a cost and environmental benefit is added to the life-cycle of the unit. The modular system is also innovative due to stacking capabilities up to three units high. This not only helps save space in site welfare areas, but also enables tighter, smaller sites to have all the welfare they require.

12

Total Site Solutions | www.murphygroup.co.uk

NATIONWIDE COVERAGE

13

Murphy Plant depot network TSS utilise the Murphy depot network – accessible 24/7 and backed up by our highly-trained service engineers.

MANCHESTER

OLLERTON

HEMEL HEMPSTEAD

LONDON

DEPOT HEMEL HEMPSTEAD

SUB DEPOT MANCHESTER LONDON

HUB OLLERTON

14

Total Site Solutions | www.murphygroup.co.uk

ENVIRONMENT AND SUSTAINABILITY

15

ENVIRONMENT AND SUSTAINABILITY

Eco spec accommodation ■ Fully insulated floor, ceiling and walls ■ Double glazed windows ■ Lighting with PIR sensors ■ Heating with PIR and timers ■ Waterless features available in wet areas Toilets ■ Waterless urinal technology that uses less water than conventional toilet blocks ■ Dual flush toilets ■ Hand dryers to reduce use of paper towels ■ Non-concussive aerated taps to minimise water usage ■ PIR lighting Waste disposal and drainage For our projects hiring TSS waste tanks, TSS provides an effluent tank emptying service in conjunction with TSS toilet blocks. This means that a steel or bunded effluent tank is placed under the TSS toilet cabin. TSS can arrange waste removal using a specialised tanker fleet capable of emptying waste tanks of up to 3,000 gallons. All waste is disposed of safely and in accordance with current waste regulations. Our service provider operates over 100 tankers throughout the country and they have effluent tankers available to meet all requests. Their tankers are managed by computerised route planning and GPS vehicle tracking. Hazardous material storage Hazardous waste is defined in the European Waste Catalogue and the List of Wastes (England) Regulations 2005. Please check your local position if your project is in Scotland

or Northern Ireland. Items considered as hazardous waste are included. These include: ■ Paints, inks and resins ■ Flammable liquids

■ Asbestos ■ Oil filters ■ Fluorescent tubes

■ Contaminated packaging residues ■ Detergents containing hazardous substances ■ Batteries and discarded electrical equipment, such as TVs and computer monitors, fridges and freezers. For further information on the removal of hazardous waste, please visit: www.environmentlaw.org.uk TSS can provide a 10’ x 8’ COSHH store that comes fully bunded with air ventilation, shelving for storage and stay back doors for safety. Spill kits come as standard. If required, the option of intrinsically safe electrical lighting and heating can be added, but this will require advance notification of up to three weeks for installation. Water conservation measures Our new eco range features a unique guttering system. A narrow gutter surrounds the upper structure of the cabin and allows water to be captured. This can then flow through to a bunded water bowser and reused for irrigation or clean treated to provide flushing water for toilets.

16

Total Site Solutions | www.murphygroup.co.uk

MOBILISATION START POINT

17

MOBILISATION START POINT

TSS should be consulted at tender stage. This enables us to design the most efficient and cost effective solution. For major projects between weeks twenty six and twenty, a planned mobilisation project plan is formulated. This instigates the start-up plan and allows reviews up to the point of award status. Please note that all sites shown in this booklet are indicative of standard set-ups and sites may vary dependent on project requirements. Contract award status Once a final approach for site set-up has been agreed, project managers in liaison with TSS produce an end-to-end mobilisation plan to work to. This follows the processes outlined on page 20. If all steps within the process map are followed, the project will commence with all of the other required elements in place. A comprehensive checklist can be found on Sharepoint at: https://murphygroup.sharepoint.com/sites/intranet/specialistcentres/murphyplant If you do not have access to Sharepoint please e-mail us for a form at: totalsitesolutions@murphyplant.co.uk

PROJECT DELIVERY SUPERVISOR

PROJECT COORDINATOR

With the project won and requisition placed the project coordinator will gather all of the detailed requirements

Liaises with the project manager to visit and assess the site

The information is then issued to the relevant service providers who will support the project

The scale is agreed and a communication plan is put in the file transfer area

Mobilisation process initiated

Total Site Solutions | www.murphygroup.co.uk

18

Total Site Solutions | www.murphygroup.co.uk

Weeks

-26 -25 -24 -23 -22 -21 -21 -20 -19 -18 -17 -16 -15 -14 -13 -12 -11 -10

-15 -14 -13 -12 -11 -10

-12 -11 -10

-9 -8 -7 -6 -5 -4 -3 -2 -1 0

-9 -8 -7 -6 -5 -4 -3 -2 -1 0 -9 -8 -7 -6 -5 -4 -3 -2 -1 0

-9 -8 -7 -6 -5 -4 -3 -2 -1 0

-7 -6 -5 -4 -3 -2 -1 0

SITE GO

-12 -11 -10

-8 -7 -6 -5 -4 -3 -2 -1 0

-6 -5 -4 -3 -2 -1 0

-5 -4 -3 -2 -1 0

DEMOB COMPLETE

17 9

THE PROCESS

How to use the time-line Throughout this guide you’ll notice the time-line. It shows thresholds, points where TSS require information to ensure mobilisation deadlines are met. A full process map can be seen on pages 21 and 22, and an overview of these thresholds shown on pages 23 and 24. Dependent on project scale (major, large, medium or small) notice requirements differ significantly. Thresholds are highlighted on the time-lines as yellow blocks. Major projects (26 weeks mobilisation and 12 weeks demobilisation) TSS should be engaged in all major project activity from tender stage. The TSS timeframe will take no longer than 26 weeks to deliver all site requirements, but early engagement will result in a better planned mobilisation. Large projects (15 weeks mobilisation and 8 weeks demobilisation) Whilst large projects are of course smaller than major, it is recommended that you liaise with TSS at tender stage. This guarantees site requirements can be comfortably met. Large projects require at least 15 weeks’ notice to ensure site delivery. Medium projects (12 weeks mobilisation and 6 weeks demobilisation) Medium projects, although only for 11 to 20 people, still require a minimum of 12 weeks’ notice. This allows accommodation and services to be on site and functional by the proposed go live date. Small projects (7 weeks mobilisation and 5 weeks demobilisation) TSS appreciate that small projects are often reactive. For site mobilisation to be right first time, it is imperative that engagement begins as early as possible. Even the smallest site set-ups require at least seven weeks’ notice to achieve successful delivery. Working together Early engagement with TSS means projects can focus on other tasks, relying upon an assured TSS service. Delivering a successfully mobilised site is a complex process and excellent pre-planning is essential. If notice periods are adhered to, TSS guarantee first-class service, right first time, and on time, every time.

20

Total Site Solutions | www.murphygroup.co.uk

TSS MOBILISATION PROCESS MAP

Request site set-up

Review quote

Quote

Site set-up request (PDF)

e-mail

Project Manager Logistics Group IT Electrical TSS Project Co-ordinator TSS Regional Supervisor

Quotation prepared

Confirmation recieved

Requirements logged

Source and arrange cabin preparation

Liaise with TSS Project Coordinator

Receive new instructions

Liaise with TSS Project Coordinator

Receive new instructions

Liaise with TSS Project Coordinator

Receive new instructions

21

Accept GO LIVE date

Authorisation of completion

Engagement survey

Arrange GO LIVE date

Send invoice to project for install against quote

Invoice

Confirm timelines

Confirm completion

Provide install service

Provide install service

Provide install service

22

Total Site Solutions | www.murphygroup.co.uk

These time-lines represent the points at which key resources need to be requisitioned. REQUISITION TIME-LINE

Mobilisation

START POINT

Large site Major site Medium site Small site -26

-25 -24 -23 -22 -21 -21 -20 -19 -18 -17 -16 -15 -14 -13 -12 -11 -

COMMUNICATIONS

ELECTRICITY

-15 -14 -13 -12 -11 -

LOGISTICS

MOBILISATION REVIEW

-12 -11 -

WASTE

WATER

23

Demobilisation

0 -9 -8 -7 -6 -5 -4 -3 -2 -1 0 -12 -11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 0

DEMOBILISATION COMPLETION DATE

SITE GO LIVE HANDOVER DATE

0 -9 -8 -7 -6 -5 -4 -3 -2 -1 0

-8 -7 -6 -5 -4 -3 -2 -1 0

0 -9 -8 -7 -6 -5 -4 -3 -2 -1 0

-4 -5 -6 -3 -2 -1 0

-7 -6 -5 -4 -3 -2 -1 0

-4 -5 -3 -2 -1 0

24

Total Site Solutions | www.murphygroup.co.uk

MAJOR PROJECTS SCALABLE SITE SOLUTIONS

-26 -25 -24 -23 -22 -21 -21 -20 -19 -18 -17 -16 -15 -14 -13 -12 -11 -10

WEEKS

-15 -14 -13 -12 -11 -10

-12 -11 -10

-9 -8 -7 -6 -5 -4 -3 -2 -1 0 -9 -8 -7 -6 -5 -4 -3 -2 -1 0

-9 -8 -7 -6 -5 -4 -3 -2 -1 0

-9 -8 -7 -6 -5 -4 -3 -2 -1 0

-7 -6 -5 -4 -3 -2 -1 0

SITE GO

-12 -11 -10

-8 -7 -6 -5 -4 -3 -2 -1 0

-6 -5 -4 -3 -2 -1 0

-5 -4 -3 -2 -1 0

DEMOB COMPLETE

25

SCALABLE SITE SOLUTIONS

Modular accommodation Modular options should be considered for projects that exceed more than fifty people. These are typically Tier 1 projects that exceed a two-year operational period. Delivering a premium facility of this type requires intensive planning and the mobilisation supervisor will take full control of the process. They will be assigned to oversee all operational requirements, from the initial enquiry through to completion of the project. This provides a single point of contact for each site. Unit types A variety of configurations are available dependent on the number of personnel required to man the site. The example overleaf shows a typical configuration, however much larger offices can be constructed. A number of optional extras can also be chosen including smoking shelters and security huts. Please see page 43 for details.

The requirements for each site vary dependent on its operational requirements and they will be customised to reflect these needs. These requirements will be ascertained by site surveys, factoring in ground conditions, personnel requirements, location and available space. Key time points The mobilisation point for this type of site is twenty six weeks from operational start date. TSS expects the site set-up to be achieved by week -1. Demobilisation activities must allow twelve weeks for major, eight for large, six for medium and five for small projects respectively. This ensures the most cost effective close down of site and allows for the strategic use of logistics in removal.

26

Total Site Solutions | www.murphygroup.co.uk

What ground preparations are required before delivery? Site access must be free of obstruction, allowing enough space for the vehicle delivering the temporary accommodation units. Suitable foundations or a level hard-standing area must be in place to accommodate units. It is site responsibility to prepare the ground prior to delivery and ensure that all temporary works designs are complete for both single and double stacked units. Usage of pad foundations depends on site conditions, total weight of the building and the imposed loads. Advice on foundation loads and positions can be given by TSS staff. The Project Delivery Supervisor will also advise you on these matters during a site inspection. The ground conditions over four points must withstand a minimum load of 48kN at each loading point between ground and unit contact. The the diagram below shows the ground bearing capacity and depth required to deliver a solid foundation using hardcore.

Maximum safe working load

48kN

Single Jackpad Support

450 x 450 = 237 kN/M 2 550 x 550 = 159 kN/m 2

50 mm

650 x 650 = 114 kN/m 2

100 mm

Ground bearing capacity

750 x 750 = 85 kN/m 2

150 mm

Depth

850 x 850 = 66 kN/m 2

200 mm

250 mm

950 x 950 = 53 kN/m 2

300 mm

1050 x 1050 = 43 kN/m 2

Specifications ■ Eco cabins

■ Stackable to three stories ■ Open plan configuration ■ WiFi system ■ Conference facilities (telephone and video) ■ Branded with all requisite site signage

■ Large scale development site ■ Quality fixtures and fittings

■ Integrated fire systems ■ Jack pads for levelling

27

MODULAR — INITIAL PLANNING This shows the various stages that must be followed prior to installation.

Planning department contact TSS Project Coordinator

The Project Coordinator contacts site with options of current stock or a decision on a new bespoke build

Drawings and time scales are agreed with a detailed quote

A requisition is sent to the TSS Project Coordinator and a CAPEX raised if required and approved

Installation commences

28

Total Site Solutions | www.murphygroup.co.uk

O/A 9758 A typical stacked modular site layout

First Floor Plan

UPVC T&T UPVC T&T

DOWN

PB Ingress

838

UPVC T&T

UPVC T&T

AC

UPVC T&T

UPVC T&T UPVC T&T

UPVC T&T UPVC T&T

3000 3000 3000

838 BB CH UPVC T&T UPVC T&T UPVC T&T

datapoints

Kitchen

23.6m² Lobby 1067

UPVC T&T UPVC T&T

UPVC T&T UPVC T&T

Each floorboxc/w

DLBU1000

BU500

1000

DLBU

1067

UPVC T&T UPVC T&T

UPVC T&T UPVC T&T

Open Plan Office (45p)

838 UPVC

2XG

113.5m²

15.5m²

838 2X5DL

838 UPVC

CH

RC

Each floorboxc/w

2XG

2NoDSSO& 4no

datapoints

UPVC T&T UPVC T&T

Server Room / Store / Office

UPVC T&T UPVC T&T

UPVC T&T UPVC T&T

11.6m²

3000

AC

AC

UPVC T&T UPVC T&T

Server Room / Store / Office

UPVC T&T UPVC T&T

UPVC T&T UPVC T&T

Print / Copy Area / Storage

11.6m²

3000

12.5m²

Meeting Room

22.8m²

AC

AC

UPVC T&T UPVC T&T

UPVC T&T UPVC T&T

UPVC T&T UPVC T&T

Office (1p-2p)

12.5m²

3000

Office (1p-2p)

A

AC

AC

UPVC T&T

UPVC T&T

UPVC T&T

UPVC T&T

This plan shows a typical stacked, modular site office solution for more than fifty site office personnel. DOWN

UPVC T&T UPVC T&T

DOWN

29

O/A 9757

PB Ingress

838

Ground Floor Plan

First Floor Plan

UPVC T&T UPVC T&T

DOWN

DOWN

838

PB

UPVC T&T

AC

UPVC T&T

UPVC T&T UPVC T&T

Female WC

11.3m²

3000 3000 3000

838 BB CH UPVC T&T UPVC T&T UPVC T&T

Kitchen

23.6m²

UPVC T&T UPVC T&T UPVC T&T UPVC T&T UPVC T&T UPVC T&T UPVC T&T UPVC T&T UPVC T&T UPVC T&T

Male WC

12.0m² Reception

DLBU1000

BU500

1000

DLBU

1067

1067

500

WU1000

WU500

UPVC T&T

838 UPVC

2XG

Lobby

15.5m²

12.7m²

838 2X5DL

838 UPVC

CH

RC

2XG

AC

UPVC T&T UPVC T&T

UPVC T&T UPVC T&T

Server Room / Store / Office

Print / Copy Area / Storage

12.5m²

11.6m²

3000

AC

AC

UPVC T&T UPVC T&T

UPVC T&T UPVC T&T

Print / Copy Area / Storage

11.6m²

3000

12.5m²

Office (1p-2p)

Meeting Room

22.8m²

AC

AC

UPVC T&T UPVC T&T

UPVC T&T UPVC T&T

Office (1p-2p)

10.9m²

3000

Office (1p-2p)

AC

AC

AC

UPVC T&T

UPVC T&T

UPVC T&T

UPVC T&T UPVC T&T

UPVC T&T UPVC T&T

DOWN

UPVC

2XGG

PB Ingress

838

30

Total Site Solutions | www.murphygroup.co.uk

-26 -25 -24 -23 -22 -21 -21 -20 -19 -18 -17 -16 -15 -14 -13 -12 -11 -10

LARGE PROJECT 21 - 50 PEOPLE — COMPLETE WORKING SITE

WEEKS

Specifications ■ Eco cabins ■ Zip boiler

■ 2 double offices ■ 3 six-person offices

Personnel 21-50 Project duration 1 to 5 years Cabins

■ PIR light fittings ■ Furnished ■ Double glazing ■ Security windows ■ Jack pads (as appropriate) ■ Lockers

■ Drying room ■ 2 open plan canteens

32’ x 10’ Anti-vandal with eco cabin option available 20’ x 8’ shower and toilet cabin Mobilisation point -15 weeks

-15 -14 -13 -12 -11 -10

-12 -11 -10

-9 -8 -7 -6 -5 -4 -3 -2 -1 0

-9 -8 -7 -6 -5 -4 -3 -2 -1 0 -9 -8 -7 -6 -5 -4 -3 -2 -1 0

-9 -8 -7 -6 -5 -4 -3 -2 -1 0

A standard set-up for rapid mobilisation, incorporating meeting rooms and extra open plan office space. An effective work environment with additional welfare facilities that allow for up to fifty people.

-7 -6 -5 -4 -3 -2 -1 0

SITE GO

-12 -11 -10

-8 -7 -6 -5 -4 -3 -2 -1 0

-6 -5 -4 -3 -2 -1 0

-5 -4 -3 -2 -1 0

DEMOB COMPLETE

31

32

Total Site Solutions | www.murphygroup.co.uk

A typical large site layout

838 2X5DL

RC CH

h&c Hooks 1800 affl

h&c Hooks 1800 affl

2L

2L

838

838

HCD

HCD

UPVC T&T UPVC T&T

UPVC T&T UPVC T&T

2 Person Office

2 Person Office

Sign-inDesk

1200x1200 Noticeboard

1200x1200 Noticeboard

h&cHooks

UPVC T&T UPVC T&T

2 Person Office

2 Person office

1200x1200Noticeboard

1200x1200Noticeboard

300mm Link

1200x1200 Noticeboard

6 Person office / meeting room

1200x1200Noticeboard

300mm Link

1200x1200 Noticeboard

m

m

Lavatories

Water Inlet/WasteOutlet throughwallprotected by steel shroud.

MaleWC

HL 3

h&cHooks 1800affl

Canteen

FemaleWC

h&cHooks 1800affl

Female WC

m

838

2L

HCD

Shroud

m

300mm Link

Waste outlet/ Water Inlet through wall

m

protected by Steel

1200x1200 Noticeboard

2X5DL IB

762

6 Person office / meeting room

h&cHooks 1800affl

1200x1200Noticeboard

300mm Link

1200x1200 Noticeboard

6 Person office / meeting room

h&cHooks 1800affl

1200x1200Noticeboard

33

do not s

1200x1200Noticeboard

h&cHooks 1800affl

Open plan canteen

UPVC T&T UPVC T&T

by steel shroud.

Water Inlet/ Waste Outlet through wall protected

Worktop@900mmaffl

h&cHooks 1800affl

1200x1200Noticeboard

HLBU1000

300mm Link

1200x1200 Noticeboard

h&c Hooks 1800 affl

Worktop @ 900mm affl DLBU1000 White goods By Others

UPVC T&T UPVC T&T

UPVC T&T UPVC T&T

Open plan canteen

by steel shroud.

Water Inlet/ Waste Outlet through wall protected

h&c Hooks 1800 affl

1200x1200 Noticeboard

HLBU1000

300mm Link

Drying room

Water Inlet/WasteOutlet throughwallprotected by steel shroud.

Waste outlet/ Water Inlet through wall protected by Steel Shroud

HL 3

HL 3

Female WC

Shroud

Shroud

Male WC

wdp

IB

IB

IB

IB

m

Waste outlet/ Water Inlet through wall

Waste outlet/ Water Inlet through wall

m

protected by Steel

protected by Steel

Lavatories

Uni-Sex Shower

m

m

m

m

m

m

m

m

2X5DL IB

762

762 2X5DL RC

762 2X5DL IB

A separate toilet and shower facility is provided in addition to the lavatories housed within the main office cabins.

Rev:

Client:

. .

Project: Anti Va 21-50 P

Title:

Plan lay

Date:

Dwg N 03.04.1 03.489

34

Total Site Solutions | www.murphygroup.co.uk

3D illustration of a typical large site for 21 to 50 people LARGE SITE

35

36

Total Site Solutions | www.murphygroup.co.uk

MEDIUM PROJECT 11 - 20 PEOPLE — COMPLETE WORKING SITE

-26 -25 -24 -23 -22 -21 -21 -20 -19 -18 -17 -16 -15 -14 -13 -12 -11 -10

Specifications ■ Eco cabins ■ Zip boiler

■ Double office ■ 2 open plan offices ■ Kitchenette / toilet ■ Open plan canteen ■ Drying room ■ 2 + 1 toilet

Personnel 11-20

Project duration Up to 12 months Cabins

■ PIR light fittings ■ Furnished ■ Double glazing ■ Security windows ■ Jack pads (as appropriate) ■ Lockers

donot scale fromdrawing

32’ x 10’ Anti-vandal with eco cabin option available Mobilisation point -12 weeks

-15 -14 -13 -12 -11 -10

donot scale fromdrawing

1200x1200 Noticeboard

h&c Hooks 1800 affl

-12 -11 -10

Worktop @ 900mm affl DLBU1000

Blind Blind Blind Blind

UPVC T&T UPVC T&T

Open plan canteen

-9 -8 -7 -6 -5 -4 -3 -2 -1 0

-9 -8 -7 -6 -5 -4 -3 -2 -1 0

-9 -8 -7 -6 -5 -4 -3 -2 -1 0 -9 -8 -7 -6 -5 -4 -3 -2 -1 0

1200x1200 Noticeboard

h&c Hooks 1800 affl

Worktop @ 900mm affl DLBU1000

-7 -6 -5 -4 -3 -2 -1 0

UPVC T&T UPVC T&T

UPVC T&T UPVC T&T

Open plan canteen h&c Hooks 1800 affl

1200x1200 Noticeboard

HLBU1000

300mm Link

h&c Hooks 1800 affl

1200x1200 Noticeboard

HLBU1000

Hooks Fitted Above Benching @ 300 Centres, 1800mm affl

HL 3 HL 3

300mm Link

Drying room

SITE GO

Hooks Fitted Above Benching @ 300 Centres, 1800mm affl

HL 3 HL 3

-12 -11 -10

2X5DL RC CH DC

Drying room

-8 -7 -6 -5 -4 -3 -2 -1 0

White

goods

By Others

2X5DL RC CH DC

-6 -5 -4 -3 -2 -1 0

-5 -4 -3 -2 -1 0

DLBU1000

These anti-vandal units can be linked or stacked to deliver a professional appearance, optimising the available space for increased efficiency.

Female WC

White

goods

By Others

Lavatories Male WC

Female WC

DEMOB COMPLETE

Blind

Lavatories Male WC

37

Entrance

h&c Hooks 1800 affl

h&c Hooks 1800 affl

Blind Blind

Blind Blind

UPVC T&T UPVC T&T

2 person office

2 person office

Sign-in Desk @ 900 affl

1200x1200 Noticeboard

1200x1200 Noticeboard

300mm Link

h&c Hooks 1800 affl

Blind Blind

Blind Blind

UPVC T&T UPVC T&T

Open plan 6 person office

h&c Hooks 1800 affl

1200x1200 Noticeboard

300mm Link

1200x1200 Noticeboard

Male WC

White

goods

HL 3

By Others

h&c Hooks 1800 affl

Canteen

Female WC

Worktop @ 900mm affl DLBU1000

White

goods

By Others

1800 affl

Water Heaters @ High Level

300mm Link

h&c Hooks 1800 affl

1200x1200 Noticeboard

Blind Blind

Blind Blind

UPVC T&T UPVC T&T

Open plan 6 person office

h&c Hooks 1800 affl

1200x1200 Noticeboard

2X5DL RC CH

38

Total Site Solutions | www.murphygroup.co.uk

3D illustration showing a typical medium sized site configuration. MEDIUM SITE

39

40

Total Site Solutions | www.murphygroup.co.uk

SMALL PROJECT 1 - 10 PEOPLE — COMPLETE WORKING SITE

-26 -25 -24 -23 -22 -21 -21 -20 -19 -18 -17 -16 -15 -14 -13 -12 -11 -10

Specifications ■ Eco cabins ■ Zip boiler

■ Open plan office ■ Open plan canteen c/w kitchenette

Personnel 1-10

Project duration Up to 6 months Cabins

■ PIR light fittings ■ Furnished ■ Double glazing ■ Security windows ■ Jack pads (as appropriate)

■ Drying room ■ 2 + 1 toilet

20’ x 8 ‘ Anti-vandal with eco cabin option available Mobilisation point -7 weeks

-15 -14 -13 -12 -11 -10

-12 -11 -10

-9 -8 -7 -6 -5 -4 -3 -2 -1 0

-9 -8 -7 -6 -5 -4 -3 -2 -1 0

-9 -8 -7 -6 -5 -4 -3 -2 -1 0 -9 -8 -7 -6 -5 -4 -3 -2 -1 0

-7 -6 -5 -4 -3 -2 -1 0

SITE GO

-12 -11 -10

-8 -7 -6 -5 -4 -3 -2 -1 0

-6 -5 -4 -3 -2 -1 0

Ideal for short-term projects accommodating up to ten people, the small

-5 -4 -3 -2 -1 0

site configuration delivers complete welfare provision for reactive projects. It is well suited for rail projects where space is limited and logistics are challenging. With extra planning it can be delivered with eco cabins to suit client requirements.

DEMOB COMPLETE

41

1200x1200 Noticeboard

500

5

500

Office

Blind

Blind

h&c Hooks @ 1800 affl

500

500

1200x1200 Noticeboard

Canteen

Worktop @ 900mm affl

h&c Hooks @ 1800 affl

Water inlet/ Waste Outlet

V

H&C hooks above bench seating @ 300mm Ctrs

Drying room

V

HL 3

10L

m

Female WC

Lavatories Male WC

HL 3

m

m

m

m

Water Heaters @ High Level

42

Total Site Solutions | www.murphygroup.co.uk

OPTIONAL EXTRAS AVAILABLE ON REQUEST

Smoking shelter

Disabled access ramp

43

Recreation area

Door canopy

Security hut

A range of optional units and site fittings are available. Our stock includes a variety of extra items. A full list of options is available by contacting us at: totalsitesolutions@murphyplant.co.uk

Safety fencing and walkways

44

Total Site Solutions | www.murphygroup.co.uk

WEEKS

-26 -25 -24 -23 -22 -21 -21 -20 -19 -18 -17 -16 -15 -14 -13 -12 -11 -10

COMMUNICATIONS

Murphy IT has developed a reliable, repeatable and rapid in-house network solution, which helps deliver a standardised set of technologies and components. This technology enables users within temporary office cabins the ability to connect remotely, seamlessly and securely to all Murphy core applications, resources and files. We believe that delivering cutting edge technology as a key enabler will position the business to efficiently surpass our competitors. The ability to immediately connect site cabins to the ‘outside’ world offers significant benefits and provides future scalability.

The IT operates using Cisco Meraki, a cloud-based system with built in malware and virus protection. Its operation is automated allowing IT policies and user configurations to automatically download and be applied. The system relies on a series of hubs. These hubs are wireless, using 3G/4G for data and they communicate with each other to create a secure VPN (Virtual Private Network). Site computers connect via WiFi allowing them to access files, e-mail and perform VOIP (Voice Over Internet Protocol) telephony. The technology optimises the type of connection it needs automatically, to ensure the best possible connection at all times.

-15 -14 -13 -12 -11 -10

-12 -11 -10

-9 -8 -7 -6 -5 -4 -3 -2 -1 0

-9 -8 -7 -6 -5 -4 -3 -2 -1 0 -9 -8 -7 -6 -5 -4 -3 -2 -1 0

-9 -8 -7 -6 -5 -4 -3 -2 -1 0

-7 -6 -5 -4 -3 -2 -1 0

SITE GO

-12 -11 -10

-8 -7 -6 -5 -4 -3 -2 -1 0

-6 -5 -4 -3 -2 -1 0

-5 -4 -3 -2 -1 0

DEMOB COMPLETE

45

The number of hubs required for sites varies depending on the size of the site and number of users. A full assessment of requirements is undertaken by Murphy IT in liaison with TSS to provide the most suitable solution.

46

Total Site Solutions | www.murphygroup.co.uk

WEEKS

-26 -25 -24 -23 -22 -21 -21 -20 -19 -18 -17 -16 -15 -14 -13 -12 -11 -10

ELECTRICAL SYSTEMS

Mains power supplies In some circumstances it is necessary to provide mains electricity to site. This will be decided in the planning stage and will be

Generators Generator needs will be assessed based on the size of the site and personnel numbers. A range of options are available. The list below shows the most commonly used, and other options are shown on the right.

-15 -14 -13 -12 -11 -10

dependent on a number of factors including geographical location and site accessibility. Specifications are developed to meet anticipated energy usage and support the number of staff on site.

-12 -11 -10

Small — 0-10 S100 — 30 kVa Medium — 11-20

-9 -8 -7

-9 -8 -7 -6 -5 -4 -3 -2 -1 0 -9 -8 -7 -6 -5 -4 -3 -2 -1 0

-9 -8 -7 -6 -5 -4 -3 -2 -1 0

T100 — 45 kVa Large — 21-50 U100 — 60 kVa Modular — 50+ V100 — 80 kVa / V120 — 80 kVa

-7 -6 -5 -4 -3 -2 -1 0

-6 -5 -4 -3 -2 -1 0

SITE GO

-12 -11 -10

-8 -7 -6 -5 -4 -3 -2 -1 0

-6

-5 -4 -3 -2 -1 0

-5

-4 -3 -2 -1 0

DEMOB COMPLETE

47

4

100 kVa

1

3

00kVa

30kVa

kVa

48

Total Site Solutions | www.murphygroup.co.uk

WEEKS

-26 -25 -24 -23 -22 -21 -21 -20 -19 -18 -17 -16 -15 -14 -13 -12 -11 -10

WATER

Mains water supplies Supplying water to your accommodation is vital for compliance with welfare regulations. Applying for a direct water supply requires a minimum of 90 days application to the local water services. This solution is suitable for sites where geographical location provides viable access to the mains water supply. Construction and integration of pipelines will be required for the supply of clean water and removal of waste. Planning and civil approval is required and time must be factored in for the approval period. Should this option be unsuitable, it will be necessary to use alternative solutions such as tanked Where a site is either too small to warrant a mains supply, or is not near to a suitable water source, TSS will provide water storage facilities by use of tanks and bowsers. Water supply for toilets and other non-potable use is augmented by rain collection systems. This assists Murphy in its goal to operate more environmentally sustainable work sites. water supplies. Water tanks

-15 -14 -13 -12 -11 -10

-12 -11 -10

Bowsers TSS provides a range of bunded bowsers to suit your requirements. Our ICB tanks are 1,000 litre portable water storage tanks with a built in pump. They can supply fresh water to cabins on sites where mains water is not available. Tanks can be placed directly under the lavatories or buried. This prevents damage and improves site appearance. Features: ■ 1,000 litre capacity ■ Heavy duty top lifting lug on all four corners ■ Tank, tube heater and electrics concealed behind lockable doors ■ Tap and external socket fitted in a recess for protection

-9 -8 -7 -6 -5 -4 -3 -2 -1 0

-9 -8 -7 -6 -5 -4 -3 -2 -1 0 -9 -8 -7 -6 -5 -4 -3 -2 -1 0

-9 -8 -7 -6 -5 -4 -3 -2 -1 0

-7 -6 -5 -4 -3 -2 -1 0

SITE GO

-12 -11 -10

-8 -7 -6 -5 -4 -3 -2 -1 0

-6 -5 -4 -3 -2 -1 0

-5 -4 -3 -2 -1 0

■ Can be double-stacked ■ Replenishment service available

DEMOB COMPLETE

49

WEEKS

-26 -25 -24 -23 -22 -21 -21 -20 -19 -18 -17 -16 -15 -14 -13 -12 -11 -10

WASTE

Waste water management Septic tanks

A septic unit is designed to fit under portable cabins where mains effluent / drainage on site is not available. This tank fits perfectly underneath cabins of all types. An excellent temporary effluent waste storage device, it can be buried or sited underneath toilet blocks, kitchens, canteens and welfare units. Tanks are space-saving and can be stored on end. Features: ■ 2 x large sealed inspection lids; to prevent spillages and odour ■ Convenient lifting eyes ■ Internal bracing ■ Easily linkable to allow creation of larger capacity tanks ■ Rigid, strong design

-15 -14 -13 -12 -11 -10

-12 -11 -10

-9 -8 -7 -6 -5 -4 -3 -2 -1 0

-9 -8 -7 -6 -5 -4 -3 -2 -1 0 -9 -8 -7 -6 -5 -4 -3 -2 -1 0

-9 -8 -7 -6 -5 -4 -3 -2 -1 0

-7 -6 -5 -4 -3 -2 -1 0

SITE GO

-12 -11 -10

-8 -7 -6 -5 -4 -3 -2 -1 0

-6 -5 -4 -3 -2 -1 0

-5 -4 -3 -2 -1 0

DEMOB COMPLETE

48 50