Previous Page  138 / 431 Next Page
Information
Show Menu
Previous Page 138 / 431 Next Page
Page Background

August 2017

7-8

City of Morgan Hill

Sewer System Master Plan

x

RM-P2

: Replace the 18-inch gravity sewer along Tennant Ave from Railroad Ave to

Monterey Road.

x

RM-P3

: Replace the 10-inch gravity sewer along La Crosse Drive / Vineyard Boulevard

from La Mar Drive to Monterey Road.

7.4 JOINT MORGAN HILL-GILROY SEWER TRUNK CAPACITY

EVALUATION

As part of this Master Plan, the Joint Morgan Hill-Gilroy Sewer Trunk (Joint Trunk) was evaluated

for capacity adequacy. The Joint Trunk has historically had capacity constraints in the portion

along California Avenue and Harding Avenue. Since the previous Master Plan, the City has

surveyed the Joint Trunk, developed additional improvement alternatives to evaluate the feasibility

of prioritizing construction, and constructed portions of a relief trunk.

The Joint Relief Trunk (Relief Trunk) was identified in the 2002 Master Plan, and subsequent

studies as a required improvement intended to mitigate existing capacity deficiencies and to

service future growth. The City has constructed Relief Trunk along California Avenue, and south

along Harding Avenue to Highland Avenue as a 30-inch parallel pipeline. The City is currently in

the process of designing the remaining 30-inch Relief Trunk from Highland Avenue to the City of

Gilroy (

Figure 7.4

).

7.5 PIPELINE CONDITION ASSESSMENT

As additional task added to the scope of the master plan, City staff requested Akel Engineering

Group to utilize existing closed-circuit television (CCTV) data to assess the condition of the

existing sewer system infrastructure. This section documents the findings and recommendations

of the condition assessment.

7.5.1

Background and Purpose

City staff have been proactively involved in the condition assessment of their pipelines, including

performing CCTV, and rating those pipelines against the NASSCO Pipeline Assessment

Certification Program (PACP). This rating system assesses pipelines based on observations from

the CCTV, and scores them from 1 to 5 based on the criticality of the observations, with 5 being

most critical. As such, City staff would like to prioritize improvement recommendations and costs

in this master plan based on the physical condition of the sewer collection system. The pipelines

that have been included in the CCTV, and which were reviewed as part of this condition

assessment, are shown graphically on

Figure 7.5

.

7.5.2

Condition Assessment Findings

The condition assessment focused on documenting major structural defects (PACP Rating 4 or 5)

and infiltration and inflow defects. Major structural defects can lead to costly pipeline failures,

while infiltration and inflow defects may contribute to sanitary sewer overflows downstream.