Paper 2: Why embrace the concept of the Safety Requirements Specification?
Institute of Measurement and Control – Functional Safety 2016
5
required to manage risk and why, because the future will cause many
occasions to ask “why?” and expect the SRS to provide the answers.
If specifications (the solution) are not linked to requirements (the
process) then how can their importance be judged by others?
Case studies.
To illustrate the above analysis and substantiate the opinions put forward in this
paper, the following examples are included
Case study 1.
Off gas from a scrubber with a vacuum unit is extracted and sent via network of
pipes to a heater or incinerator. The specification required shut-off valves in the
gas line to both the heater and incinerator. An over temperature hazard had
been identified whereby hot gas could be drawn back into the scrubber.
Therefore, the valves were specified as tight shut-off and both valves must
successfully close to eliminate the hazard. During the device review the
requirement for tight shut-off was questioned. Minor leakage of the valves was
considered along with the length of pipe, lack of lagging and consequent
temperature drop. It was determined that although tight shut-off was an
appropriate design feature, it was not a requirement for achieving the safe state
for this hazard. Tight shut-off is a significant decision to make. The failure rate
is increased, testing almost certainly requires removal and meeting the SIL
target might impose further redundancy requirements. On its own tight shut-off
was a simple requirement but when considered as a whole safety function the
full impact is realised.
Case study 2.
Although the application of IEC 61511 to fire and gas systems is the subject of
much debate, this example illustrates a point. The FPSO had a complex
system of fire protection systems and associated firewater pumps. The cause
and effect matrix was the reference for logic solver configuration. Three of the
effects were associated with starting the firewater pumps and an associated
note said "pumps will start on demand". On questioning what this note meant it
was clear that a significant layer of complexity was not addressed by the
cause-and-effect matrix. After significant discussion a four-page description
was agreed regarding overall firewater pump operation and logic solver
configuration.
Case study 3.
Tank overfill prevention has gained significant focus since the Buncefield
disaster of December 2005. This application involved unloading methanol from
a ship to bulk storage tanks onshore, movement of methanol between storage
tanks and movement of methanol to a smaller tank which fed the process units.
The specification received stated "on detection of high-level close the inlet
valve" for each of the four tanks involved. It is important to only include the
minimum measurements and actions required to detect and protect against a