Ten-Year Network Development Plan 2017 Main Report |

29

Listing of projects not in NDPs,

with infrastructure gap addressed

According to Article 8 of Regulation (EC) No. 715/2009, the Community-wide

network development plan shall build on national investment plans. This does not

prevent, from a legal perspective, that projects are submitted to the TYNDP although

they are not yet part of a national investment plan. Indeed, TYNDP is a non-binding

exercise that allows an EU-wide perspective on projects.

In TYNDP 2017, as part of the project data collection, project promoters have been

requested to indicate if their projects were part of the national development plan

(NDP). The way Project Promoters have answered may vary depending on the

interpretation of the question. Projects in the validation phase of the respective

NDPs led to either a positive or negative response to this request. For future data

collections, ENTSOG should further clarify what is expected from project promoters

in answering such request.

In case of projects which are not part of the relevant NDPs, TSOs or project promoters

have provided the reasoning behind the project is not part of a NDP.

Information on infrastructure gaps addressed by the project was also part of the

information collected from project promoters.

Following ACER recommendation, and based on the project information as received

from the project promoters in the TYNDP project data collection, ENTSOG has

included a new Annex A3. Although this information was previously available in

Annex A1, this provides a targeted overview of the TYNDP projects for which were

reported as not included in NDPs, together with the reason for non-NDP inclusion

as well as the infrastructure gaps addressed by these projects, as provided by the

promoters.

About 75% of the TYNDP projects are reported as listed in NDPs. It is worth

mentioning that in the case of about 40% of the projects not part of the relevant

NDP, the reasons for non-inclusion are outside the control of the Project Promoters

(e. g. country is outside EU, Project Promoters are not TSOs, country does not have

a NDP, etc).

NRA Comments on the TYNDP 2017 projects

As part of its Opinion, ACER offered national regulatory authorities (NRAs) to provide

comments on TYNDP projects that had significant differences

 1)

in the characteris-

tics in comparison to the information available in their NRA (last NDP or other

source). These comments are available as an annex to ACER Opinion

 2)

and provide

valuable additional information on projects, as a supplement to the promoter

information as provided as part of TYNDP Annex A.

The comments from the NRAs in particular reflect recent project information, NRAs

own views on project promoter information, and in some occasion identification of

incorrect data in project submission.

The comments regarding incorrect data have been incorporated in the final version

of the TYNDP, within Annex A.

Regarding recent project information, it is a standard feature of projects that they

keep on evolving as time passes. In TYNDP, the information on projects has to be

frozen at one point in time, to ensure that the development process is performed in

a timely manner in line with the TYNDP publication timeline.

 1) ACER Opinion specifies, page 26 footnote 52: NRAs were invited to indicate significant differences (not due to natural

evolution of a project) in the characteristics (data fields) in comparison to the information available in their NRA

(last NDP or other source). ENTSOG’s TYNDP 2017 data is as of 25 May 2016, when data collection process was closed

for this TYNDP.

 2)

http://www.acer.europa.eu/Official_documents/Acts_of_the_Agency/Opinions/Opinions/ACER%20Opinion%2006-2017.pdf