New NTS developments for taking over gas from the Black Sea shore

General Information

Promoter

SNTGN Transgaz SA

Operator

SNTGN Transgaz S.A.

Host Country

Romania

Status

Planned

Website

Publication Approval Status

Approved

Sponsors

SNTGN Transgaz SA

100%

TRA-N-964

Project

Pipeline including CS

Non-FID

Update Date

07/05/2016

Non-Advanced

Description

The project consists of the NTS extension for creating an additional overtaking point for the offshore Black Sea blocks gas. In this respect it is

considered the building of a transmission pipeline approximately 25 ² 30-km long, from the Black Sea shore to the existing T1 international

transmission pipeline.

Regulatory Decisions and

similar material conditions

Schedule

Start Date

End Date

Pre-Feasibility

Feasibility

FEED

Market Test

12/2016

Permitting

Supply Contracts

FID

Construction

Commissioning

2019

2019

NDP and PCI Information

Part of NDP

Yes (Development Plan for the National

GTS 2016 - 2025)

NDP Number

7.6

Currently PCI

No

CBCA Decision

No

Market Survey

Not Relevant (no CBCA decision)

Third-Party Access Regime

Considered TPA Regime

Regulated

Considered Tariff Regime

Regulated

Applied for Exemption

No

Exemption Granted

Not Relevant

Exemption in entry direction

0.00%

Exemption in exit direction

0.00%