Project GO4LNG LNG terminal Gothenburg
General Information
Promoter
Swedegas AB
Operator
Swedegas AB
Host Country
Sweden
Status
Planned
Website
Project's URLPublication Approval Status
Approved
Sponsors
Swedegas AB
100%
LNG-N-032
Project
LNG Terminal
Non-FID
Update Date
04/05/2016
Advanced
Description
A small-scale LNG terminal, including connection to the transmission grid, placed in the Gothenburg harbour, with flexible send out by rail, truck,
bunkering and regasification.
Regulatory Decisions and
similar material conditions
Capacity Increments Variant For Modelling
Point
Operator
Year
From Gas System To Gas System Capacity
Gothenburg LNG
Swedegas AB
2020
LNG_Tk_SE
SE
26.0 GWh/d
Schedule
Start Date
End Date
Pre-Feasibility
01/2012
Feasibility
01/2012
06/2012
FEED
04/2016
10/2016
Market Test
01/2013
Permitting
10/2013
05/2014
Supply Contracts
12/2016
FID
01/2017
Construction
01/2017
01/2020
Commissioning
2020
2020
NDP and PCI Information
Part of NDP
No (Not applicable for Sweden. There is no
NDP. )
NDP Number
Currently PCI
Yes (8.6)
CBCA Decision
Yes (2015-10-01)
Market Survey
Open Season(2013-02-27)
Third-Party Access Regime
Considered TPA Regime
Regulated
Considered Tariff Regime
Regulated
Applied for Exemption
No
Exemption Granted
No
Exemption in entry direction
0.00%
Exemption in exit direction
0.00%
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM
Page 502 of 620
Current TYNDP : TYNDP 2017 - Annex A