Further enlargement of the BG³RO³HU³AT transmission corridor (BRUA) phase 3

General Information

Promoter

SNTGN Transgaz SA

Operator

SNTGN Transgaz S.A.

Host Country

Romania

Status

Planned

Website

Publication Approval Status

Approved

Sponsors

SNTGN Transgaz SA

100%

TRA-N-959

Project

Pipeline including CS

Non-FID

Update Date

22/06/2016

Non-Advanced

Description

'HYHORSPHQW RI JDV WUDQVPLVVLRQ FDSDFLW\ RQ WKH 2QHûWL ² Coroi ² +DġHJ ² 1ĄGODF FRUULGRU GHSHQGLQJ RQ WKH DYDLODEOH JDV TXDQWLWLHV DW WKH %ODFN

Sea shore or from other on-shore blocks. The development of this gas transmission corridor requires: the rehabilitation of some of the NTS

existing pipelines; replacement of some of the NTS existing pipelines with new pipelines or the building of new pipelines installed in parallel with

the existing ones; development of 4 or 5 new compressor stations having a total installed power of approximately 66- 82.5MW.

Regulatory Decisions and

similar material conditions

Capacity Increments Variant For Modelling

Point

Operator

Year

From Gas System To Gas System Capacity

Csanadpalota 2

SNTGN Transgaz S.A.

2023

HU

RO

128.7 GWh/d

SNTGN Transgaz S.A.

2023

RO

HU

128.7 GWh/d

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM

Page 497 of 620

Current TYNDP : TYNDP 2017 - Annex A