Azerbaijan, Georgia, Romania Interconnector - AGRI

General Information

Promoter

AGRI LNG Project Company

SRL (RO)

Operator

AGRI

Host Country

Romania

Status

Planned

Website

Project's URL

Publication Approval Status

Approved

Sponsors

GOGC (GE)

25%

MVM (HU)

25%

ROMGAZ (RO)

25%

SOCAR (AZ)

25%

TRA-N-376

Project

Pipeline including CS

Non-FID

Update Date

07/05/2016

Non-Advanced

Description

The solution for the transmission of natural gas from Caspian region through the territory of Azerbaijan and Georgia, its liquefaction and

transportation via Black Sea to Romania and Hungary and potentially to other European markets; As a "standby LNG project", AGRI will implement

and operate the LNG portion: - the "natural gas the liquefaction Facilities") on Georgian Shore; - transport of LNG from Georgian shore to Romanian

shore; - the "natural Re-gasification terminal" on Romanian Shore. The project is pure LNG project and has no posibility to include technical details

so please see below: ================================= For LNG Project: Maximum Annual Capacity: 8.0 bcm/y; Maximum sendout

capacity: 22.0 milion cm/d; Storage capacity: 160,000.0 cm of LNG; Maximum ship cargo size: 2 x 140,000.0 mc of LNG;

==================================

Regulatory Decisions and

similar material conditions

Capacity Increments Variant For Modelling

Point

Operator

Year

From Gas System To Gas System Capacity

AGRI / Constanta (RO)

AGRI

2026

GEa

RO

240.0 GWh/d

Comment: Regazification terminal

AGRI / Poti (GE)

AGRI

2026

GE?

GEa

240.0 GWh/d

Comment: Liquefaction terminal

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM

Page 492 of 620

Current TYNDP : TYNDP 2017 - Annex A