Time Schedule

Grant Obtention Date

01/10/2014

Delay Since Last TYNDP

Delay Explanation

PCI Details

PCI Benefits

Project changes the capability to transmit gas across the borders of the member states concerned by at least 10%, compared to the situation

prior to the commissioning of the project, Project concerns investment in reverse flow capacity

General Criteria Fulfilled

Yes

Specific Criteria Fulfilled

Competition, Market Integration, Security of Supply, Sustainability

Specific Criteria Fulfilled Comments

Pipelines and Compressor Stations

Pipeline Section

Pipeline Comment

Diameter (mm) Length (km) Compressor Power (MW)

%ĝHFODY &= 3RäWRUQi 5HLQWDO &= $7

The pipeline length at CZ side is approx. 12 km and at AT side

is approx. 49 km; no compressor station is considered at CZ

side.

800

12

Total

12

Schedule

Start Date

End Date

Pre-Feasibility

Feasibility

FEED

03/2012

06/2018

Market Test

06/2015

Permitting

Supply Contracts

FID

Construction

Commissioning

2020

2020

NDP and PCI Information

Part of NDP

Yes (NDP 2016-2025)

NDP Number

TRA-N-133

Currently PCI

Yes (6.4)

CBCA Decision

No

Market Survey

Not Relevant (no CBCA decision)

Third-Party Access Regime

Considered TPA Regime

Regulated

Considered Tariff Regime

Regulated

Applied for Exemption

No

Exemption Granted

Not Relevant

Exemption in entry direction

0.00%

Exemption in exit direction

0.00%