Time Schedule

Grant Obtention Date

29/04/2015

Delay Since Last TYNDP

Delay Explanation

PCI Details

PCI Benefits

Project changes the capability to transmit gas across the borders of the member states concerned by at least 10%, compared to the situation

prior to the commissioning of the project, Project concerns investment in reverse flow capacity

General Criteria Fulfilled

Yes

Specific Criteria Fulfilled

Competition, Market Integration, Security of Supply, Sustainability

Specific Criteria Fulfilled Comments

Pipelines and Compressor Stations

Pipeline Section

Pipeline Comment

Diameter (mm) Length (km) Compressor Power (MW)

7YUGRQLFH &= +Dģ &= 3/

The pipeline length at CZ side is approx. 207.4 km (Tvrdonice-

+Dģ 8SJUDGH RI WKH H[LVWLQJ FRPSUHVVRU VWDWLRQ %ĝHFODY &=

is needed.

1,000

207

24

Total

207

24

Schedule

Start Date

End Date

Pre-Feasibility

Feasibility

FEED

06/2014

02/2017

Market Test

05/2012

Permitting

09/2010

11/2017

Supply Contracts

FID

Construction

Commissioning

2019

2019

NDP and PCI Information

Part of NDP

Yes (NDP 2016-2025)

NDP Number

TRA-N-136

Currently PCI

Yes (6.1.1, 6.1.12)

CBCA Decision

Yes (2014-10-17)

Market Survey

Other(2012-05-17)

Third-Party Access Regime

Considered TPA Regime

Regulated

Considered Tariff Regime

Regulated

Applied for Exemption

No

Exemption Granted

Not Relevant

Exemption in entry direction

0.00%

Exemption in exit direction

0.00%