Capacity4Gas (C4G) ² CZ/SK

General Information

Promoter

NET4GAS, s.r.o.

Operator

NET4GAS, s.r.o.

Host Country

Czechia

Status

Planned

Website

Publication Approval Status

Approved

Sponsors

Czech Republic

NET4GAS, s.r.o.

100%

Slovakia

eustream, a.s.

100%

TRA-N-918

Project

Pipeline including CS

Non-FID

Update Date

20/05/2016

Advanced

Description

The project Capacity4Gas (C4G) represents 3 specific projects, which deal with increase of cross-market capacities at 3 different borders and were

developed in the context of a non-binding market survey performed at the beginning of 2016. The market survey was focused on an assessment of

the need for new transmission capacity between the Czech Republic and adjacent market areas. The 3 projects are (1) C4G ² DE/CZ, i.e. entry capacity

increase between DE (Gaspool) and CZ, (2a) C4G ² CZ/SK, i.e. exit capacity increase between CZ and SK, (2b) C4G ² CZ/AT, i.e. exit capacity increase

between CZ and AT. The projects (2a) and (2b) are alternatives.

Regulatory Decisions and

similar material conditions

Capacity Increments Variant For Modelling

Point

Operator

Year

From Gas System To Gas System Capacity

Lanžhot

NET4GAS, s.r.o.

2019

CZ

SK

650.0 GWh/d

Comment: The incremental capacity represents approx. X capacity extension at CZ/SK border

(the project C4G-CZ/SK is alternative to X capacity extension at CZ/AT border,C4G-CZ/AT).

Commissioning date is set 2019 for the availability of the capacity 2020

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM

Page 67 of 620

Current TYNDP : TYNDP 2017 - Annex A