Benefits

Main Driver

Market Demand

Main Driver Explanation

Benefit Description

Pipelines and Compressor Stations

Pipeline Section

Pipeline Comment

Diameter (mm) Length (km) Compressor Power (MW)

C4G - DE/CZ

The project comprises several technical measures, which leads

factually to entry capacity increase between DE (Gaspool) and

CZ. The incremental capacity represents approx. entry capacity

extension between the market areas of DE (Gaspool) and CZ.

Total

Schedule

Start Date

End Date

Pre-Feasibility

Feasibility

FEED

10/2015

06/2018

Market Test

02/2016

Permitting

Supply Contracts

FID

Construction

Commissioning

2019

2020

NDP and PCI Information

Part of NDP

Yes (NDP 2017-2026 (new project))

NDP Number

TRA-N-752

Currently PCI

No

CBCA Decision

No

Market Survey

Not Relevant (no CBCA decision)

Third-Party Access Regime

Considered TPA Regime

Regulated

Considered Tariff Regime

Regulated

Applied for Exemption

No

Exemption Granted

Not Relevant

Exemption in entry direction

0.00%

Exemption in exit direction

0.00%

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM

Page 66 of 620

Current TYNDP : TYNDP 2017 - Annex A