Expected Gas Sourcing
Russia, The interconnection allows access to all gas sources from the neighbouring countries.
Comments about the Third-Party Access Regime
The transmission tariff will be regulated according to EU regulations.
Benefits
Main Driver
Market Demand
Main Driver Explanation
Enormous development of the national gasification systemand hence increased consumption/demand on the market.
Benefit Description
-Security of supply -Diversification of sources -Development of the region (reversible gas pipelines).
Time Schedule
Grant Obtention Date
Delay Since Last TYNDP
Delay Explanation
MER JSC Skopje for the first time submits this project in the TYNDP. The possibility of delay is due to the interstate procedures and financing.
Barriers
Barrier Type
Description
Others
Barriers regarding the implementation of the projects have not been encountered.
Schedule
Start Date
End Date
Pre-Feasibility
Feasibility
04/2009
07/2010
FEED
07/2010
Market Test
Permitting
Supply Contracts
FID
Construction
Commissioning
2022
2022
NDP and PCI Information
Part of NDP
Yes (Work Program of the Government of
R.Macedonia)
NDP Number
N/A
Currently PCI
No
CBCA Decision
No
Market Survey
Not Relevant (no CBCA decision)
Third-Party Access Regime
Considered TPA Regime
Regulated
Considered Tariff Regime
Regulated
Applied for Exemption
No
Exemption Granted
Not Relevant
Exemption in entry direction
0.00%
Exemption in exit direction
0.00%
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM
Page 608 of 620
Current TYNDP : TYNDP 2017 - Annex A