Time Schedule
Grant Obtention Date
13/05/2015
Delay Since Last TYNDP
No
Delay Explanation
#Error
PCI Details
PCI Benefits
Project changes the capability to transmit gas across the borders of the member states concerned by at least 10%, compared to the situation
prior to the commissioning of the project
General Criteria Fulfilled
Yes
Specific Criteria Fulfilled
Competition, Market Integration, Security of Supply, Sustainability
Specific Criteria Fulfilled Comments
Pipelines and Compressor Stations
Pipeline Section
Pipeline Comment
Diameter (mm) Length (km) Compressor Power (MW)
Eskishehir (Turkey)-Greece Border
1,219
460
46
Georgia/Turkey border- Eskishehir
1,442
1,347
46
Total
1,807
92
Schedule
Start Date
End Date
Pre-Feasibility
08/2012
Feasibility
01/2013
03/2013
FEED
09/2012
05/2014
Market Test
12/2013
Permitting
04/2014
07/2014
Supply Contracts
06/2019
FID
12/2013
Construction
06/2014
06/2019
Commissioning
2018
2019
NDP and PCI Information
Part of NDP
No (TANAP Project is not directly
constructed by Turkish Government
whereas it is executed by a private legal
entity. However, there are referrals to
TANAP Project in National Development
Plans of Turkey since TANAP has a
strategic importance.)
NDP Number
Currently PCI
Yes (7.1.1)
CBCA Decision
No
Market Survey
Not Relevant (no CBCA decision)
Third-Party Access Regime
Considered TPA Regime
Not Applicable
Considered Tariff Regime
Not Applicable
Applied for Exemption
No
Exemption Granted
No
Exemption in entry direction
0.00%
Exemption in exit direction
0.00%